Local Food Production
Pilot-Credits SSpc82:Local food productionposted by OSLEIDE WALKER on
Does anyone have any experience developing a successful Integrated Pest Management (IPM) Plan for this pilot credit. Do you know exactly what measures or components are required?
Refrigerant Atmospheric Impact
EBOM-v4 EAc8:Enhanced refrigerant managementposted by Meier Corporate Account on
Good Morning, I am currently working on this credit and something in the guide (page 301) does not make much sense to me... At the top of the page in Table 3 it has the calculation for the RAI as
Combined Purchasing
EBOM-v4 MRp1:Ongoing purchasing and waste policyposted by Ryan Hoffman on
The project in question is the north building of a 2-building, 1 million sf facility.
what all is included in material cost
NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materialsposted by Brianna Brandsen on
Is labor to deliver (i.e. drive time, time to unload materials, and / or shipping costs from suppliers) and / or unload materials on a job site included in the material cost?
Special Needs Student Equipment (Schools 2009)
Pilot-Credits EQpc78:Design for active occupantsposted by Cynthia Kaplan on
Has anyone had success with this pilot credit by including "active" furniture for special needs students?
LEED approved paints and coatins
NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Luis Galvan on
If a lacquer or varnish meets the low VOC criteria required by IEQc4.2 but does not state that it qualifies to meet LEED requirments.
Baseline system for hybrid service hot water system
NC-2009 EAp2:Minimum Energy Performanceposted by Vernon Smith on
Our Proposed project (LEED 2009 NC) has a hybrid service hot water system that uses a water-source heat pump as the primary hot water generator and has a heat exchanger as a backup downstream of t
Any HAP Expert?
NC-2009 EAp2:Minimum Energy Performanceposted by Khaled Fouda on
I use Carrier-HAP and according to ASHRAE 90.1 G.1 #4, all baseline HVAC fans should be running continuously when the space is occupied and cycled when the space is unoccupied.
Existing buidling assembly
Schools-2009 EAp2:Minimum Energy Performanceposted by soham babu on
If we are not knowing existing assembly values can we go with ASHRAE 90.1 values for existing assembly. USGBC will approve ?
Adding carpet to LEED Platinum NC building
posted by Alireza Anvari on
Hi, I'm new here and new in LEED, I apologize for my ignorance. I work as a PM in a LEED Platinum NC building. We are planning to install carpet in the top floor hall way.