Historic Bldg Renovation being done in phases, Bldg reuse calcs
NC-2009 MRc1.1:Building Reuse—Maintain Existing Walls, Floors and Roofposted by Debra a. Lombard on
I'm working on behalf of a GC on a complicated historic renovation and new construction project that's being done in several phases with separate contracts between Owner and GC.
WEc2: Time frame for functional reclaimed water systems
NC-2009 WEc2:Innovative Wastewater Technologiesposted by Brian Bartholomew on
Under the Bird's Eye View here for WEc2, there is a citation of LEED Interpretation #10012 made on 05/09/2011 which states "projects may only count future infrastructure such as reclaimed water sys
MRc5 Material Tracking/Documentation
CS-2009 MRc5:Regional Materialsposted by Maggie Hogan Skaug on
RE: usgbc.org/leedonline, CS2009 MRc5 I do not see a form or calculator for material tracking or other forms/upload requirements for this credit documentation.
searching out no voc floor sheathing and mdf
NC-2009 IEQc4.4:Low-Emitting Materials—Composite Wood and Agrifiber Productsposted by Phil Vanderloo on
I was hoping someone can direct me to a resource, available to Sacramento Ca., for compliant, (no voc or urea formaldehyde), 1 1/8" T&G plywood floor sheathing. Thank You
Phased Flush Out
Schools-NC-v4 EQc4:Indoor air quality assessmentposted by Cynthia Kaplan on
We have a phased reno/add school project that would prefer to earn IEQ 4 by way of post occupancy flush out.
FSC Wood COC
NC-2009 MRc7:Certified Woodposted by Andy Prestridge on
We have received the FSC invoice for some of our FSC plywood and our subcontractor had it delivered to his shop a few miles away and then brought it to the site.
MRpc69 Attainable in the New Construction Project
Pilot-Credits MRpc69:Construction and demolition waste managementposted by Vanessa Cardona on
This credit was readily attainable for a new residential building located in Manhattan. Six streams were recycled by tracking waste throughout the construction phase of the project.
Views exculsion for High Bay Window areas
Schools-2009 IEQc8.2:Daylight and Views—Viewsposted by David Sundersingh on
We are in the early stages of design for a Career Compact Center, this has 3 workshop areas with high bay windows for natural lighting.
Project has all 5 Categories
Schools-2009 WEc4:Process water use reductionposted by Sara Zoumbaris on
Hi all, My project has all 5 categories installed (dishwasher with racks, pre rinse etc..), however one of the products is above the maximum limit.
Annual Energy Cost
NC-2009 EAc2:On-Site Renewable Energyposted by Sarah Thompson on
I am trying to figure out which cost to put in here. Another post said it was savings, although I can't find anything under the credit intent or resources for this specific item.