SS C6.1: Bio Retention Dead Storage Offset
EBOM-2009 SSc6:Stormwater Quantity Controlposted by Robert Howell on
Past conversations have said that the volume stored in the soil mix and the dead storage above the soil mix (below the overflow) in bio-retention basins can be used to offset the runoff volume incr
Additional information
posted by Barry Giles on
Since completing this version 4 Platinum we have been successful on a second V4 Platinum at One Sansome Street, San Francisco for the Barker Pacific Group.
Building Envelope Commissioning
Retail-CI-v2009 EAc1.5:Optimize energy performance - building envelopeposted by Lance Barron on
We are working with a client who would like to get LEED credit for building envelope commissioning, but which has not pursued enhanced commissioning.
PPM versus other units of measurement
Pilot-Credits EApc66:Community contaminant prevention - airborne releasesposted by Jennifer Berg on
The current credit uses ppm units for all equipment. This is not a common measurement used or documented for generators.
Hotels: separate surveys & corrective measures 4 guests & FTEs?
NC-2009 IEQc7.2:Thermal Comfort—Verificationposted by Susan Di Giulio on
HI, Continuing the Hotel conversation, the 2013 IEQ matrix indicates that guestrooms, front desk and BOH - housekeeping areas should be included for IEQc7.2.
SSc2
NC-2009 SSc2:Development Density and Community Connectivityposted by Erika Duran on
I am working towards the SSc2 credit. Two buildings are currently under construction and floor and site area are unavailable. What should I do? Thanks, Erika
3.2 at a Group Project
CI-2009 SSc3.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Russell Remy on
I currently have a group project LEED-CI in which one building has changing facilities and showers meant for both building tenants use.
Sounds transmission - Ceilings and Floors
NC-v4 EQc9:Acoustic performanceposted by Adam Stoker on
The LEED v4 acoustics calculator expands on the guidance provided in the credit and reference guide with respect to the sound transmission requirements and associated calculations.
Garage Lighting LPDs
NC-2009 EAp2:Minimum Energy Performanceposted by Joseph Snider on
ASHRAE lists .2 w/sf for garage spaces in Space by Space, and .3 w/sf in Building Area method.
ID 10209 Mixed-use Building with office not residential use
NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Jeffry Magnuson on
Our project is a 122,900 sf building for a single office user. There is 5,000 sf of retail space at the ground floor, currently not leased.