Occupancy date for Core and Shell

CS-2009 IEQc3:Construction IAQ Management Plan—During Construction
posted by  Edgar Arevalo  on 

Regarding the MERV-8 filter section of this credit, which is for a C&S project, no tenant occupancy dates have been established.  Should I just wait til we get the first tenant occupancy d

0

Ventilation Requirement for High Rise Residential

NC-v4 EQp1:Minimum indoor air quality performance
posted by  Jay Murray  on 

Question: Is it necesary to hard duct ventilation air into each bedroom within the apartment?

0

Interior Partitions Option 2: Strategy F without movable partitions?

NC-v4 EQc6:Interior lighting
posted by  Cindy Quinn  on 

Has anyone had success earning Interior Lighting Option 2: Strategy F with a project that doesn't have movable partitions?  Our project was denied this strategy because we don't have movable p

1
Thu Jul 4, 2019, 1:26 am

Definition of Inpatient Units

Healthcare-v4 MRc8:Design for flexibility
posted by  Neumann Monson  on 

Our project is a Behavioral Health Community Access Center. We're considering using the Horizontal Expansion option under design for flexibility.

0

Building-level energy metering

NC-v4 EAp3:Building-level energy metering
posted by  Tim Hemsath  on 

How does USGBC enforce the commitment to sharing with USGBC the resulting energy consumption data and electrical demand data (if metered)...

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4459 thumbs up
Mon Jul 1, 2019, 11:36 am

v4_Low Emitting Materials Calculator

CI-v4 MRc5:Building product disclosure and optimization - material ingredients
posted by  Thomas Bennett  on 

I am trying to fill out this LEED calculator for the 5 HVAC materials that we are using on a project, 440 Gasket Tape, Duct Sealant DP1015, Oatey No 5.

0

Mandatory Requirements and Applicable Exceptions: Section 8.1.5

CI-v4 EAp2:Minimum energy performance
posted by  Waleed AlGhamdi  on 

In a LEED v4 CI project, we have a floor that will architecturally stay the same. New HVAC and new lighting fixtures (same ceiling and placement though).

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4459 thumbs up
Fri Jun 28, 2019, 3:00 pm

Interior Reuse - shared walls with other businesses

CI-v4 MRc2:Interiors life-cycle impact reduction
posted by  Lou Niles II  on 

Hello Can anyone give some advice on including Both sides or one side of interior walls for a Tenant Improvement where the other side of the wall is a space not in the scope.