NC-v4 EAc3:Advanced energy metering
posted by  Pooja Sannamani  on 

Hi, my project is in design and current proposes to meter lighting and exterior lighting together.  The exterior lighting is very small so the electrical engineer is pushing on whether we real

0

Solar energy production

NC-v4 EAc5:Renewable energy production
posted by  Nithya Madan  on 

Scenario 1 - Is solar energy produced inside the campus but outside of the project boundary considered towards the credit?

6
Founder & Senior Consultant
Viable LLC
LEEDuser Premium Member
12 thumbs up
Tue Nov 19, 2019, 9:02 pm

Zones served by mutli-zone unit but is exhausted separately

NC-2009 IEQp1:Minimum IAQ Performance
posted by  Edgar Arevalo  on 

This may be nothing, but should I still count for zones that are served by a multizone unit but the ventilated air is not recirculated back to the unit?  The air is pretty much exhausted throu

5
Energy Engineer
ads ENGINEERS, DPC
LEEDuser Basic Member
21 thumbs up
Tue Nov 19, 2019, 3:03 pm

RCI Visual Inspections - STILL???

NC-v4.1 MRc5:Construction and Demolition Waste Management
posted by  Kimberlee Ilardi  on 

We have a project that is using a Certified Commingled Recycling Facility for their single-stream recycling and they are giving us visual inspections, with a breakdown of each waste strea

3
Vice President, Practices & National Sustainability Leader
Whiting-Turner
LEEDuser Premium Member
0 thumbs up
Fri Nov 15, 2019, 7:56 pm

Exterior Noise Control

Pilot-Credits EQpc57:Enhanced acoustical performance - exterior noise control
posted by  Alan Burt  on 

This project had several challenges related to exterior noise, it is in a busy area near downtown and at the time exposed to higher than typical noise levels from the exhaust system serving an unde

0

VOC/Emissions documentation for Casework/Millwork

CI-v4 EQc2:Low emitting materials
posted by  Tracy Marquis  on 

I am looking for some clarification pertaining to the VOC and emissions requirements for Casework and Millwork. 

7
Senior Sustainability Strategist
Jacobs Engineering
LEEDuser Premium Member
149 thumbs up
Wed Nov 13, 2019, 10:21 pm

LEED Documentation /Back Up

NC-2009 MRc5:Regional Materials
posted by  Heather Young  on 

I have been recently told that I need more proof on the distance of the Steel Mill to the job site to justify regional materials.

5
Environmental Business Development- LEED AP BD&C
Nucor Corporation
LEEDuser Basic Member
132 thumbs up
Wed Nov 13, 2019, 9:44 pm

O+M Table of Contents requirement for v4 Fundamental commisioning

CI-v4 EAp1:Fundamental commissioning and verification
posted by  Robert Fernandez  on 

I provided our primary LEED review with all of the following individually as each has its own upload to meet the intent of the credit but am being requested for an O+M table of contents for Fu