LEED EBOM EA1 Case 2C
EBOM-2009 EAc1:Optimize Energy Performanceposted by Magda Aghababyan on
I am working on a facility that cannot obtain an Energy Star score due to building type. I wish to use the Case 2 Option 2C using a set of comparable buildings.
Discharging the rainwater to municipality facilities.
CS-2009 SSc6.1:Stormwater Design—Quantity Controlposted by mohamed magdy on
Does discharging the collected rainwater to municipality facilities will help with achieving the requirements for credit 6.1 & 6.2? we are following Case1 - path 1, we will reclaim the rainwat
Denied prerequisite
posted by Charalampos Giannikopoulos on
After two rounds of review EAp2 was denied although we reckon that we had totally addressed all comments of the preliminary review and additionally the issues described as outstanding in the final
Assemblies
NC-2009 MRc4:Recycled Contentposted by David Brown on
In idiot terms could someone please tell me what makes up an "assembly". I am a glazing contractor working on a LEED project. I have two items needing LEED submittals for the MR4 credit.
KS and KD Values in Table 1 - Cannot find
NC-2009 WEc1:Water Efficient Landscapingposted by Amal Iqbal on
Hello, I checked on page 185 of the BD+C Reference as mentioned by William in a previos post, and did not see anything about species factors.
RE: LI#10397
NC-2009 EAc2:On-Site Renewable Energyposted by Joe Manganelli on
Hi All, Does anyone have any experience with LI#10397? This LI# stipulates an alternative compliance path for facilities that have 60% or more non-regulated loads. QUESTION 1: I cannot find any
100% irrigation requirement met through treated waste water
NC-2009 WEc1:Water Efficient Landscapingposted by Yusuf Turab on
I find the credit language very confusing.
RE: Feeding renewable energy into the project
NC-2009 EAc2:On-Site Renewable Energyposted by Joe Manganelli on
Hi All, We have a campus with a substation on-site (on owner's property) that will be owned by the local utility.
EAp2
NC-2009 EAp2:Minimum Energy Performanceposted by sherif el adly on
We are working on a huge project in Riyadh, to meet EAp2 we sould look for a water cooled chiller due to the area of the project and the challenge to reach a COP near to 8 to meet the 10% from base
Exception G3.1.1.c and zones with minimum air changes
NC-2009 EAp2:Minimum Energy Performanceposted by Phil Stafa on
Hello: I have a question related to exception G3.1.1.c which states that a separate single System 3 should be used for zones with pressurization relationships or minimum circulation rates.