The overlap activities between CxA and CM Consultant

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Panupant Phapant  on 

Hi Can anyone share the CxA practice for LEED project in USA or other countries as we see that there are the overlap activities between the construction management consultant and CxA for LEED proje

6
Default Avatar
Technical Manager
VILANDCO
LEEDuser Basic Member
2 thumbs up
Mon Aug 29, 2016, 10:38 pm

Enhanced and Fundamental Comissioning

NC-v4 EAc1:Enhanced commissioning
posted by  Isabel Santos  on 

Dear all, Regarding the Commissioning Authority, if aiming to do Enhanced Commissioning, can the CxA be part of the LEED Consultant team, considering that the team has been involved in providing c

3
Mon Aug 29, 2016, 10:16 pm

Rainwater Management

NC-v4 SSc4:Rainwater management
posted by  Maria Glädt  on 

We are planning to follow option 2 (Natural Land Cover Conditions). The area consists mainly in clay with very low infiltration capacity.

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Mon Aug 29, 2016, 2:29 pm

WELL AP if you are LEED AP

WELL v1 Building Standard Tip Sheet
posted by  Maria Peralta  on 

Hi, I have seen on the web if you are LEED AP have discount to make the AP WELL . Is it true? I don't know how to recognize as LEED AP when making payment . Thank you

6
President, LEED AP, WELL AP
Entegra Development & Investment, LLC
LEEDuser Premium Member
43 thumbs up
Mon Aug 29, 2016, 2:12 pm

How to simulate qualified area for IEQc8.1 at both 9 am and 3pm

CS-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Cathy W  on 

Option1-simulation. The result of ecotect shows the qualified regulary occupied area is 84% at 9 am, 83% at 3 pm.

2
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Fri Aug 26, 2016, 3:09 pm

shop applied adhesive in a laminate flooring

NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Melissa Merryweather  on 

Our product uses a laminated flooring product. If the laminating adhesive and the finish product are both factory- applied, then do we need VOC tests?

4
Fri Aug 26, 2016, 2:15 pm

High Rise Residential with mixed mode ventilation

NC-v4 EQp1:Minimum indoor air quality performance
posted by  Nancy Henderson  on 

We have several high rise residential projects that use a several conditioning and ventilation system.

3
Default Avatar
Managing Member
ArchEcology, LLC
LEEDuser Basic Member
67 thumbs up
Thu Aug 25, 2016, 9:50 pm

Valuation of Recycled Content

CI-v4 MRc4:Building product disclosure and optimization - sourcing of raw materials
posted by  Rebecca Pinto  on 

I would like some clarification on how to calculate recycled content as the v4 Reference Guide is ambiguous, in my opinion. For example, on p.274 of the ID+C ref.

3
Default Avatar
Sustainability Consultant, P.Eng.
Mission Green Buildings
LEEDuser Basic Member
0 thumbs up
Thu Aug 25, 2016, 6:53 pm

LEED Interpretation 5253

NC-2009 EAp2:Minimum Energy Performance
posted by  Monique Belmer  on 

I'm working on an appeal and the reviewer is asking me why our baseline heating went up significantly between the initial submission and our review response model.

3
Thu Aug 25, 2016, 4:03 pm

Denied EAp2

NC-2009 EAp2:Minimum Energy Performance
posted by  Charalampos Giannikopoulos  on 

After two rounds of review our model was denied because according to the reviewer’s comment it still “it remains unclear whether the energy savings modeled for space heating are justified”.

5
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Aug 25, 2016, 3:42 pm