LEED Dynamic Plaque: Is it Sustainable?
posted by Michael Ozenich on
As we explore building energy efficiency, is one more energized device plugged into the internet of things really a strategy for sustainability?
Expansion area
NC-2009 PIf3:Occupant and Usage Dataposted by Gustavo De las Heras Izquierdo on
Our LEED Project Boundary includes a future expansion area. Should we include the expansion area as "building footprint"? Calculations in credit SSc5.1 will depend on this decision.
Vista Users Out of Luck
posted by Cynthia Kaplan on
On 9/26/14 I lost the ability to view credit tempolate forms in LOL v3. Three weeks and 163 phone minutes later, the final verdict from GBCI is to buy a new computer.
Regularly Occupied Space + Basement View Access
NC-2009 IEQc8.2:Daylight and Views—Viewsposted by Ryan Kurlbaum on
We are doing a zero-lot line project in NYC on a very narrow site.
regulalry occupied in DCs
Data-Centers-NC-v4 EQc7:Daylightposted by Ehsan Baharvand on
Dear, Currently I'm reviewing a Datacenter plan which is pursuing for LEED DC v4 certification. What if the design does not include any regularly occupied space?
Some question about roof garden.
NC-2009 SSc7.2:Heat Island Effect—Roofposted by Shenhao Li on
I have a hotel project in china. Our client will build a roof garden. Some areas of roof garden is vegetated roof, and other area will be construct as lane, tennis court or other things.
percentage of vertical fenestration
NC-2009 EAc1:Optimize Energy Performanceposted by Francesco Passerini on
I have a doubt concerning the percentage of vertical fenestration I have to consider for Table G3.1 5.c. Let me give you an example.
Core and Shell project with public bike scheme adjacent
CS-v4 LTc5:Access to quality transitposted by Sean Hogan on
Our project seeking C&S certification for and existing building redevelopment.
Future Bike Racks
NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Sadie Martin on
We are working on a phased project, we are currently in constrcution of the first phase and have started design on the second phase.
Process energy cost
NC-v4 EAp2:Minimum energy performanceposted by Charline SEYTIER on
Hi everyone, Reading the v4 reference guide, it seems that the default process energy being 25% of total energy cost for the baseline disappeared from the requirements. Have you also noticed it?