Forum quick links
Central Plant - Condenser Loop
CS-2009 EAc1:Optimize Energy Performanceposted by MKK LEED on
We are working on a project with two buildings on one site, one commercial C&S, one Hotel.
existing not occupied parts
NC-2009 EAc1:Optimize Energy Performanceposted by Francesco Passerini on
In the building that I’m modeling some parts were existing prior to the project, some parts are new.
prescriptive efficiency requirement for purchased heat
CI-2009 EAc1.3:Optimize Energy Performance—HVACposted by Bethany Beers on
If all of my zone equipment and my chillers prescriptively comply with the Core Performance Requirements, but for HHW we have heat exchangers with purchased steam from a district source, then do I
Example of DAYLIGHT AND Views
NC-2009 IEQc8.1:Daylight and Views—Daylightposted by bojana kovacevic on
I am biginner in LEED, for the first time I am meeting with some things.
Integrative Process-Value Engineering
Pilot-Credits PC60:Integrative Processposted by Susan Coy on
Do you use Value Engineering in documenting this process?
Mix LEED NC and LEED CS within LEED Campus?
posted by Nelina Loiselle on
We have a project that has six buildings on it. The owner wants five of them to be CS, and one of them to be NC. Are we able to mix rating systems within an overall LEED Campus registration?
Using v4 requirements on a v3 project
NC-v4 LTc4:Surrounding density and diverse usesposted by Brightworks Sustainability on
Our project is hoping to use the v4 criteria (diverse uses) to meet the requirements for a v3 project.
margin
NC-2009 IEQc8.1:Daylight and Views—Daylightposted by Francesco Passerini on
In DesignBuilder for the daylight simulation you have to impose a value for the parameter "margin", which is defined in the following way: Enter the margin (in m or ft) around the zone boundaries w
Pursuing option 2, path 2
CS-2009 WEc1:Water Efficient Landscapingposted by Andrey Kuznetsov on
Dear colleagues, maybe my question will be stupid, but I hadn't found a strict answer, so I'm a little bit confused. We have a project that has no permanent irrigation system, only a has a hose bi
Final Review Denial with no Preliminary Comments?
posted by Nita Christopher on
We were recently denied a credit in the Final Review Phase on the basis of information that was presented in the Preliminary Review Phase that GBCI had no comments upon.