case 2. Residential and Hospital Projects Only- RequirementsNC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Controlposted by Veronika Sundberg on Jun 14, 2011, 5:29 am
Hi, I have a question regarding case 2. Residential and Hospital Projects Only. In the requirement for the prerequiset 8 bullets are listed that needs to be met. The four first ones are... Last reply: Veronika Sundberg, Sep 19, 2011, 5:12 am |
|
Warehouse ClassificationEBOM-2009 EAp2: Minimum Energy Efficiency Performanceposted by Prudence Ferreira on Jul 21, 2011, 3:55 pm
We are trying to classify a winery. One of the areas is used for barrel fermentation, and is temperature controlled anywhere from 55-75 degrees based on the fermentation process. Would this... Last reply: Jenny Carney, Sep 16, 2011, 3:33 pm |
|
Energy Bills are the Entire Site and Not Broken Down by BuildingEBOM-2009 EAp2: Minimum Energy Efficiency Performanceposted by Cynthia Fowler on Aug 9, 2011, 2:39 pm
My project building is one of 40+ on a company's campus/site. They do not purchase electricity on a building-by-building basis, but for the entire site. My project building is metered and the... Last reply: Jenny Carney, Sep 16, 2011, 3:30 pm |
|
countertops CSI classificationNC-2009 MRc4: Recycled Contentposted by Annette Bellafiore on Mar 9, 2010, 4:55 pm
The guidelines for MRc3 - 7 indicate that only items in Division 3 - 10, 31 and 32 should be included in the calculations unless you want to include all furniture. However, it seems like... Last reply: Benjie Herrera, Sep 16, 2011, 7:50 am |
|
Looking for an exampleNC-2009 IEQc8.1: Daylight and views - daylightposted by Eamon Geary on Sep 8, 2011, 2:49 pm
In the course of the 30+ LEED projects I have participated in, I have never successfully achieved this credit. Recently, an internal group has been working together to figure out what we can... Last reply: Eddy Santosa, Sep 15, 2011, 12:17 pm |
|
Transient Occupants (specifically students)EBOM-2009 WEp1: Minimum Indoor Plumbing Fixture and Fitting Efficiencyposted by Ashley Chiang on Aug 8, 2011, 7:04 pm
I understand the different occupancy types and the default fixture use values; however, what I do not understand is how I am suppose to get a somewhat accurate estimation of a occupancy daily... Last reply: Ashley Chiang, Sep 15, 2011, 12:02 pm |
|
Recycled Content/Certified WoodCI-2009 MRc4: Recycled Contentposted by Méabh Browne on Sep 7, 2011, 1:01 pm
Hi, Last reply: Méabh Browne, Sep 15, 2011, 4:29 am |
|
Hi The credit defines comfortNC-2009 IEQc6.2: Controllability of systems - thermal comfortposted by SUNG SU KIM on Aug 17, 2011, 7:17 pm
Hi The credit defines comfort according to the four primary comfort criteria identified by ASHRAE 55-2004: air temperature Last reply: SUNG SU KIM, Sep 15, 2011, 2:45 am |
|
Construction Waste Management || Clean FillNC-2009 MRc2: Construction Waste Managementposted by Andrew Gil on Aug 29, 2011, 1:19 pm
Apologies if this topic has already been addressed (and, on that note, I have a suggestion: As the number of postings grows & grows, it might be very helpful to be able to search within a... Last reply: Susan Walter, Sep 14, 2011, 1:49 pm |
|
Separate Demolition Package from Construction PackageCI-2009 MRc2: Construction Waste Managementposted by Alison Y Rivenburgh on May 6, 2010, 1:34 pm
A large project with a building slated for demolition - the demo package is completely separate from the construction package, and will take place half/full year in advance of construction. The... Last reply: Susan Walter, Sep 14, 2011, 1:42 pm |