Pavement and TreesNC-2009 MRc2: Construction Waste Managementposted by Michelle Teague on Sep 8, 2011, 9:46 pm
The definition of construction and demolition debris on page 362 of the technical guide says "pre-existing structures". I understand the exclusion of land clearing debris, such as soil,... Last reply: Tristan Roberts, Sep 26, 2011, 10:32 pm |
|
NEBB Certification Required?NC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Nathan Lee on Sep 8, 2011, 8:48 pm
A question about NEBB Certification. Is the... Last reply: Tristan Roberts, Sep 26, 2011, 9:58 pm |
|
Required Number of Construction Inspections?NC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Benjamin Tressler on Sep 19, 2011, 11:19 am
Does LEED specify a required number of... Last reply: Tristan Roberts, Sep 26, 2011, 9:52 pm |
|
Control types in Group Multi-occupant SpacesEBOM-2009 IEQc2.2: Controllability of systems - lightingposted by Jenny Carney on Mar 7, 2011, 5:48 pm
All, Word on the street is that there's a new standard teams are being held to for the types of controls that are allowed in group spaces. Historically, pretty much any kind of control was... Last reply: Andrea Marzullo, Sep 26, 2011, 3:52 pm |
|
LZ2 10 foot “hot spots”NC-2009 SSc8: Light Pollution Reductionposted by Vincent Pieri on Sep 26, 2011, 3:36 pm
We are owrking on a project on previously developed land that we have established as complying with IESNA LZ2. The surface parking for the project runs along the Southern edge of our site, which... |
|
Floor area calculatingNC-2009 IEQc8.1: Daylight and views - daylightposted by Mohamed Ravuthar, LEED AP, BD+C on Sep 25, 2011, 9:52 am
I'm using the Option 2 - Prescriptive Approach for this credit, In particular room has 6 windows and each side two and one side no windows. Now i have calculated the window area and floor area... Last reply: TODD REED, Sep 26, 2011, 10:14 am |
|
Regularly occupied spaces for stadiumsNC-2009 IEQc8.1: Daylight and views - daylightposted by Adriana Hansen on Sep 22, 2011, 5:53 pm
We are in doubt about the classification of regularly occupied spaces for a stadium. Last reply: TODD REED, Sep 26, 2011, 10:11 am |
|
Existing FinishCI-2009 MRc1.2: Building reuse - maintain interior nonstructural elementsposted by Sara Neff on Apr 28, 2011, 3:29 pm
I looked through the reference guide for a definition of 'finished,' but I couldn't find one, so I'm hoping someone here can help: I have a CI project that is moving into a space that has... Last reply: Raymond Loo, Sep 25, 2011, 6:05 am |
|
Meeting humidity requirements with mixed modeNC-2009 IEQc7.1: Thermal comfort - designposted by Carly Ruggieri on Aug 16, 2011, 10:42 am
Does anyone have any experience or guidance for documenting compliance with ASHRAE 55 with a mechanically conditioned, naturally ventilated building? When windows are open, the required humidity... Last reply: Patrik Lazzari, Sep 23, 2011, 11:49 am |
|
Help needed: Process Energy / Water- 25% Default vs. ActualNC-2009 EAc1: Optimize Energy Performanceposted by Dan Prows on Feb 10, 2010, 4:09 pm
We have a child care center in the SE US. We did very well on envelope, lighting, and mechanical design (53% reduction in those areas). The building has a commercial kitchen with several... Last reply: Marcus Sheffer, Sep 23, 2011, 9:23 am |