Help w/ wrangling RECs.

CS-2009 EAc2:On-site Renewable Energy
posted by  Brian Salazar  on 

Preface: LEED CS v3.0 Project in Massachusetts. Our project is designed to produce 16% on-site renewable energy. The energy is fed directly into the building and used by the building.

18
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jul 9, 2015, 9:05 pm

Questions about High-rise residential LEED Energy Modeling

NC-2009 EAc1:Optimize Energy Performance
posted by  Tommy Xing  on 

Hi, I’m working on a High-rise residential LEED energy modeling project now. I have a question regarding the lighting.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jul 9, 2015, 5:44 pm

Compliant area

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  David Browne  on 

Perhaps this a dumb question, but would someone please clarify this for me? I am currently attempting this credit on two projects.

2
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Thu Jul 9, 2015, 2:07 pm

HVAC system wasn't running during construction

NC-2009 IEQc3.1:Construction IAQ Management Plan—During Construction
posted by  Juanita Garcia  on 

If the HVAC system wasn't running during construction of a new building, what is the requirement for documentation? We have dated checklists documenting that the HVAC system wasn't running and that

2
Thu Jul 9, 2015, 12:47 am

Exterior Shading Devices

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  Sara Zoumbaris  on 

Hello LEED Users, I am working on a project with a majority of the exterior being composed of aluminum curtain wall.

2
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Wed Jul 8, 2015, 8:50 pm

Partially Occupied Warehouse

NC-2009 IEQp1:Minimum IAQ Performance
posted by  Annalise Reichert  on 

I am working on a project that has a 45,000 SF unconditioned warehouse and utilizes natural ventilation.

3
Wed Jul 8, 2015, 6:39 pm

G3.1.1 Exception a

NC-2009 EAp2:Minimum Energy Performance
posted by  Haojie Wang  on 

I have a convention center project where it has a exhibit hall with high process load. It is larger than 20k ft2.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Jul 8, 2015, 4:33 pm

Reserved parking on existingcampus parking area outside building

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  LEEDme Lorenzi  on 

We have a new office project inside a campus, there is an existing big parking area serving the campus not adiacent to the building, no parking are allocated inside our LEED boundary and not new pa

2
Default Avatar
Building Performance Specialist
WSP Built Ecology
LEEDuser Basic Member
2 thumbs up
Tue Jul 7, 2015, 9:29 pm

Stormwater inspection

EBOM-2009 SSc6:Stormwater Quantity Control
posted by  Charalampos Giannikopoulos  on 

Both uploads SSc6-3 and SSc6-4 require the provision of “a copy of the most recent stormwater inspection and a log showing that any needed maintenance or repairs were performed within 60 days of th

3
Tue Jul 7, 2015, 2:07 pm

Energy recovery from a nearby data center?

NC-2009 EAp2:Minimum Energy Performance
posted by  Haojie Wang  on 

We have a project that is planning to use energy recovery from a nearby data center. The rest of the heat and cooling are provided by a district plant.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Jul 6, 2015, 4:30 pm