Post a question or comment
Filter by location
Forum
Topic
Replies
Recent
1
Thu Aug 1, 2019, 6:56 pm

Additions to Existing Cold Storage Facility

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Dustin Norton  on 

I am working on a project that includes a large existing cold storage facility that will essentially double in size after renovations.

2
Sustainability Program Manager
Primus Design Services, LLC
LEEDuser Premium Member
40 thumbs up
Wed Jan 23, 2019, 7:49 pm

Flush out using building emergency exhaust ventilation system

Retail-CI-v4 EQc4:Indoor air quality assessment
posted by  Mahesh Shankar  on 

The project is a retail store which is not flushing out the space using outdoor air. The exhaust ventilation system of the building is used to 

0

Option 2 - Example

NC-v4 EQc5:Thermal comfort
posted by  Konstantina Kalliakoudi  on 

Hello to all,

I have an European project and I will follow Option 2. But I have difficulties in understanding the Method.

1
Fri Dec 20, 2019, 6:02 pm

Leed v4 BD+C examples

LEED Rating System Selection
posted by  Konstantina Kalliakoudi  on 

Hello to all,

Is there a link where I could find real examples of buildings as registered for LEED New Construction v4 BD+C?

0

Materials inside the building

NC-v4 EQc2:Low emitting materials
posted by  Konstantina Kalliakoudi  on 

Hello to all,

In my understanding this credit "Low emitting materials" concerns materials inside the building, and not outside. Is this right?

Thanks

0

Furniture always in scope of work?

NC-v4 EQc2:Low emitting materials
posted by  Raphael Sperry  on 

I've noticed that the LEED reference guide says "Furniture is considered part of the scope if it is installed at the time of occupancy, regardless of who specified or provided it." And I've never

5
Wed Jan 23, 2019, 12:20 am

DHW limitations

NC-2009 EAp2:Minimum Energy Performance
posted by  Jorge Lopez de Obeso  on 

Hi, I've been having some trouble regarding DHW modeling.

5
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Jan 22, 2019, 10:01 pm

Case 2 Option 2C

EBOM-2009 EAc1:Optimize Energy Performance
posted by  Patrick Cellie  on 

I am working with a convention center that is currently Silver certified under the v2009 EBOM rating system. 

3
Default Avatar
Sustainability Consultant
AECOM
LEEDuser Basic Member
0 thumbs up
Tue Jan 22, 2019, 9:14 pm