Can a building going for re-certification attempt additional credits that are not performance based
EBOM-v4.1 SSc3:Light Pollution Reductionposted by Frank Weiss on
I understand that a building attempting re-certification is awarded 10 points for their past certification. My question is can a building attempting re-certification using Version 4.1 also at
About LEED-ND Thesis
ND-v2009 NPDc2:Compact developmentposted by Mustafa Kucuk on
Hello to everyone. I am writing a thesis on LEED-ND and I need to give more information about LEED-ND. (How to get a certificate? What are the criteria and sub-titles?
On site visits required?
NC-v4 EAp1:Fundamental commissioning and verificationposted by Kasandra Martin on
The project I am hired to commission is a day drive. Is it possible to only review the contractors tests or is on site necessary or required?
Indoor Water Use Reduction Calculator - Occupant Inputs for Core Restrooms in Office Building
posted by Karena Broman-Ballas on
I am working on the Water Reduction Credit for a project and confused on how to input the Occupant Percentages for central core restrooms. The instructions on the Water Reduction Calculator s
TABLE 6.8.2B Minimum Duct Insulation
NC-v4 EAp2:Minimum energy performanceposted by Francesco Passerini on
I want to verify TABLE 6.8.2B Minimum Duct Insulation considering the thermal resistance of a cylindrical wall, which is determined according to the logarithmic equation you can see
Industry wide EPD vs. Product Specific EPD
NC-v4 MRc2:Building product disclosure and optimization - environmental product declarationsposted by Caitlin Hutton on
Hello, I am attempting to achieve option one of the MRc2 credit meaning we need a total of 20 products from 5 different manufacturers.
Hempcrete
posted by Chris Flint Chatto on
Curious if folks know of any resources on hempcrete, specific to durability. We have a one-story carbon-neutral operational energy project where the design team and client have bought into th
Reverberation times in warehouse spaces
NC-v4.1 EQc9:Acoustic Performanceposted by Jamie Dubbe on
Are reverberation times applicable to reg occupied warehouse spaces if the room type (warehouse) is not included in Table 2. Reverberation time requirements?
Walkable Project Site - Historic Building Exemptions
NC-v4 INc1:Innovationposted by Sara Goenner Curlee on
The Walkable Project Site innovation credit provides possible exemptions from two of the requirements for historic buildings. The typical building needs to meet eight of the nine requirements.
Interior Lighting Dimming controls in Multi-use spaces
NC-v4 EQc6:Interior lightingposted by Summer Gorder on
The interior lighting of our projects has 3 zones for dorm rooms, but has dimming with manual on/ automatic off controls. There are also daylight zones.