Log in
Forum » CI-2009 EAc2
Topic

Contractual Relationship

CI-2009 EAc2: Enhanced Commissioning
posted by Brian Smith on Aug 26, 2013, 8:09 pm

The owner is looking for CI-2009 Enhanced...

Last reply: Scott Bowman, Sep 6, 2013, 5:47 pm

Commissioning of Process Equipment

CI-2009 EAc2: Enhanced Commissioning
posted by Graham Langton on Aug 8, 2013, 12:00 pm

'Commissioning is required for all systems and equipment installed as part of the tenant’s project scope'... Is it the case that for a building who's primary function is the support of a...

Last reply: Scott Bowman, Aug 20, 2013, 11:44 am

CxA qualification?

CI-2009 EAc2: Enhanced Commissioning
posted by Torsten Biernat on Jul 15, 2013, 12:59 pm

We have a project (

Last reply: Torsten Biernat, Jul 15, 2013, 4:05 pm

EAc2 Submission Requirements

CI-2009 EAc2: Enhanced Commissioning
posted by John Steingraeber on Jun 11, 2013, 2:36 pm

I am very interested in pursuing LEED CI certification for a buildout of my firm's offices. This will be my/our first LEED project. I am generally confident that we can achieve basic LEED...

Last reply: John Steingraeber, Jun 11, 2013, 5:39 pm

Fundamental and Enhanced Commissioner

CI-2009 EAc2: Enhanced Commissioning
posted by Susan F. on Jun 6, 2013, 12:29 pm

We have a project that is about 125,000 sf and are working with a consultant that is developing the...

Last reply: Scott Bowman, Jun 6, 2013, 3:01 pm

Question regarding the OPR and BOD

CI-2009 EAc2: Enhanced Commissioning
posted by Robert Calloway on Mar 18, 2013, 12:01 pm

We have a client that has the Owners Project Requirements (...

Last reply: Scott Bowman, Mar 18, 2013, 3:48 pm

Systems Manual

CI-2009 EAc2: Enhanced Commissioning
posted by Frank Weiss on Dec 5, 2012, 12:24 pm

I was envisioning the Systems Manual to be an O&M manual with drawings, equipment manuals etc. Upon...

Last reply: Scott Bowman, Dec 6, 2012, 9:04 am

Enhanced Commissioning Action Steps

CI-2009 EAc2: Enhanced Commissioning
posted by Garrett Billings on Oct 12, 2011, 7:53 pm

in the process above just points. We will let this forum know as they get submitted. Log in or register to post comments Emily Catacchio Sustainability Specialist Wight and Company LEEDuser Basic Member 610 thumbs...

Last reply: Susan Walter, Oct 20, 2011, 11:47 am