TFA (Treated Frtesh air unit)- Energy ModelingCI-2009 EAc1.3: Optimize energy performance - HVACposted by SAMY Chamy on Sep 7, 2016, 3:27 am
Dear all:- Our project have installed with VRF with TFA Unit Due to TFA unit usage we have significant saving in HVAC because outdoor air supply temperature is very low now we have... Last reply: Marcus Sheffer, Sep 12, 2016, 9:50 am |
|
LEED CI- HVAC Syatem selection and Fan power ModelingCI-2009 EAc1.3: Optimize energy performance - HVACposted by SAMY Chamy on Aug 24, 2016, 7:47 am
Dear All:- How to select the Baseline HVAC system for LEED CI Project and how I calculate the fan power for fan interlocked with HVAC system Can we us the 7Group fan power... Last reply: Marcus Sheffer, Aug 24, 2016, 10:55 am |
|
Energy ModelingCI-2009 EAc1.3: Optimize energy performance - HVACposted by SAMY Chamy on Aug 13, 2016, 7:49 am
Dear All:- How to do energy modeling for LEED CI In LEED CI the energy saving is compared for Space heating and Cooling only, 1.Am I Correct Last reply: Marcus Sheffer, Aug 22, 2016, 9:10 am |
|
LEED CI- Energy Modeling TermsCI-2009 EAc1.3: Optimize energy performance - HVACposted by SAMY Chamy on Aug 18, 2016, 7:47 am
Dear All:- Greetings I need some clarity in terms in the terms used in "LEED ID + C ref guide page no 172" what is meant by Last reply: Marcus Sheffer, Aug 19, 2016, 11:29 am |
|
energy modelingCI-2009 EAc1.3: Optimize energy performance - HVACposted by Bethany Beers on Dec 18, 2015, 9:43 pm
We have a tenant fit out of a single floor in an 8 story building. The new design is an energy efficient chilled beam system, and the central plant remains unchanged. Do I need to include the... Last reply: Marcus Sheffer, Aug 9, 2016, 10:21 am |
|
Demonstrate Savings for CRAC UnitsCI-2009 EAc1.3: Optimize energy performance - HVACposted by Gabriela Crespo on Aug 5, 2016, 1:04 pm
Dear all, Same project as before, Central Chilled Water System, not in our scope. The only HVAC equipment in our scope are 2 CRAC units for the office's SITES. If we want to demonstrate... Last reply: Marcus Sheffer, Aug 6, 2016, 2:33 pm |
|
Interpretation ProblemCI-2009 EAc1.3: Optimize energy performance - HVACposted by Maria Isabel Conde on Jul 8, 2016, 12:46 pm
We have a problem with the interpretation of the information necessary to apply for this credit. Credit requirement explain that I have to meet one of the following: Air handlers that... Last reply: Maria Isabel Conde, Jul 12, 2016, 2:45 pm |
|
Active Controls with a Fan Coil Unit SystemCI-2009 EAc1.3: Optimize energy performance - HVACposted by Ciaran McCabe on Jul 5, 2016, 11:26 am
For a Fan Coil Unit system, with outdoor air being provided adjacent to the rear of the unit will the outdoor fresh air rate (from the main... Last reply: Marcus Sheffer, Jul 11, 2016, 5:26 pm |
|
LEED Retail CI EAc1.3 zoning and controlsCI-2009 EAc1.3: Optimize energy performance - HVACposted by Francisco Aguirre on Jul 11, 2016, 4:55 am
Hi, I am working on a retail project with a... Last reply: Marcus Sheffer, Jul 11, 2016, 1:07 pm |
|
Equipment not list on CPGCI-2009 EAc1.3: Optimize energy performance - HVACposted by Maria Isabel Conde on Jul 1, 2016, 5:53 pm
Our project has a WSHP bigger than 135000 btu/h. According to CPG table 2.9.2 the efficiency required for WSHP up to 135000 btu/h is 14 EER and the WSHP of our project has a 14.1 EER. ... Last reply: Maria Isabel Conde, Jul 5, 2016, 12:23 pm |