CUP in group project
CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliancesposted by Brightworks Sustainability on
I'm working on CI group project that is also using a central utility plant. My understanding is that each building must show compliance individually for lighting power density reduction.
Wastewater
NC-2009 WEc3:Water Use Reductionposted by Alejandro Macias on
I m using the "water use reductions calculator" to document the WEp1 and WEc3. But in the project im working we will be reusing waste water for the WC and urinal flushing.
Energy Rater
posted by Gustavo De las Heras Izquierdo on
Hallo, we want to certify a home outside the U.S.
recessed walk off mat
NC-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by Bomin Kim on
We are specifying a recessed walk off mat for the building in the vestibule (8' long). I remember that if the walk off mat is 10', a point is granted.
Urinals on residencial
NC-2009 WEc3:Water Use Reductionposted by Alejandro Macias on
I m working on a dormitory for kids.
CUP question
CI-2009 EAc1.1:Optimize Energy Performance—Lighting Powerposted by Brightworks Sustainability on
We have a group CI project - 4 floors of one building and 1 smaller floor of a second building.
On-site restoration
NC-v4 SSc2:Site development - protect or restore habitatposted by Anaïs P on
Have the 30% of areas with native and adaptated vegetation to be in the same place of the previously developped areas?
Number of IAQ samples required ?
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Michael Boyle on
Our project consists of (5 townhouse + multipurpose room). This is considered as one building.
Providing water quality treatment to meet credit requirements
CS-v4 SSc4:Rainwater managementposted by Martin Stowell on
Our project provides water quality treatment of a majority of the stormwater prior to discharging from the stormwater best management practices at the site.
Credit 7.1 and 7.2
NC-2009 SSc7.1:Heat Island Effect—Non-Roofposted by Alejandro Macias on
I am working on a dormitory Project and it has different buildings (one for the kitchen, one for administration, girls dormitory….).The roof of this buildings are connected with each other, so almo