drainage area for sediment basin

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Hongyun Zhou  on 

when calculating the volume of sediment basin, what is the drainage area? Should I use footprint of the building or total land area of LEED boundary?

5
Mon Feb 12, 2018, 10:06 am
6
Mon Feb 12, 2018, 9:37 am

Direct vs indirect measurements

NC-2009 EAc5:Measurement and Verification
posted by  Cesar Ruiz  on 

Hi everyone, We are working on a Residential New Construction Project, compound of more than 100 apartments, pursuing Option D - Calibrated Simulation.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4458 thumbs up
Fri Feb 9, 2018, 6:37 pm

European project - example of signage

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Maria Perzon  on 

Our project would like to get a credit for prefered parking. As I can see in the European Alternative Compliance Path (ACP) all Euro 6 cars fulfill the demands.

4
PhD
Bengt Dahlgren AB
LEEDuser Basic Member
0 thumbs up
Fri Feb 9, 2018, 10:28 am

Successful Option 4 with Zipcar?

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Geoffrey Brock  on 

Has anybody heard of a successful option 4 using zipcar?...I'm concerned about the "use restriction" requirement mentioned in previous comments. Has this ever been achieved?...

4
Default Avatar
LEED Consultant
The Green Engineer
LEEDuser Basic Member
188 thumbs up
Fri Feb 9, 2018, 10:21 am

MRc2 Construction Waste Management

CI-2009 MRc2:Construction Waste Management
posted by  Michael Roth  on 

I have comingled waste and diverted metals.  One recycler sorts CMU, wood, paper/cardboard and metal off-site and records are kept in CYDs.  The other two recycle centers do Ferrous metal

4
Thu Feb 8, 2018, 9:55 pm

Glitch

Schools-NC-v4 SSc8:Joint use of facilities
posted by  James Carr  on 

Under the Credit Language tab this page shows SSc7, Site Master Plan, and under Site Master Plan the Credit Language is for Joint Space.

4
CEO
Green Commons, LLC
LEEDuser Expert
586 thumbs up