Forum quick links
Treating CUP as a DES?
posted by Irina Foster on
Hi, I am working on a LEED Healthcare project. The hospital building is phase 1 of a number of phases within a large master plan area.
Commissioning Walk-in Freezers / Coolers
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Richard Woodward on
We have a mixed use new office / commercial kitchen project with owner occupiers.
Calculating Vot in Credit Template
CI-2009 IEQp1:Minimum IAQ Performanceposted by Rick Servoss on
The Template calculates Vot by dividing Voz by Ev. ASHRAE 62.1 2007 arrives at Vot by dividing Vou by Ev, not Voz.
M&V Plan - Specific Acceptable Range(s) of Error
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Marina Andrade on
Hello, I just got the review comment requesting the “specific acceptable range(s) of error”, follow the comment bellow. “TECHNICAL ADVICE: Please revise the Measurement and Verification Plan, as
Design and Build Contract
posted by Ameet AA on
I am working on multiple building campus level projects which fall under same contract and same owner.
Audits Around the World
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by Jenny Carney on
All, I'm trying to compile a list of energy audit providers outside of the US.
Air cooled chillers and other air cooled equipment.
NC-2009 EAp2:Minimum Energy Performanceposted by Rudolph Carneiro on
Question: If I have an air cooled chiller selected at non-ARI conditions that has a full load efficiency of 3.0 COP, does it comply with the minimum efficiency requirement of 2.8 COP from ASHRAE -
Innovation points no longer recognized?
NC-2009 IDc1:Innovation in Designposted by Kris Phillips on
I have conflicting information on a few Innovation points that have been achieved on certain projects, but are apparently being denied on current projects being deemed "too easy" by the GBCI review