Log in
Forum » NC-2009 EAp1
Topic

Equipments to be Commissioned for Fundamental Commissioning

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Daisuke Miura on Oct 10, 2024, 9:31 pm

Hi, I have a question regarding the scope of equipments to be commissioned for Fundamental Commissioning. 

LEED guidelines specifies Mechanical (HVAC&R), plumbing, Electrical (...

Last reply: Andrey Kuznetsov, Oct 24, 2024, 6:28 am

Performing Commissioning Activities 3 years after occupancy

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Gaston Viau on Feb 15, 2018, 6:52 am

Hi!

Our NC-2009 project it's a 16,000sqf office building located in California.

The project has been finished and occupied 3 years ago. However, the Commissioning activities were...

Last reply: Nadia Azzam, Feb 20, 2024, 3:01 pm

Change of Fundamental Commissioning Agent

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Ilana Judah on Sep 16, 2014, 9:28 am

We are working on a project that is now under construction. Fundamental Commissioning was started by one party, with Enhanced Commissioning being undertaken by a second party. The owner has now...

Last reply: Craig Graber, Nov 11, 2022, 11:01 am

Fundamental Commissioning of On-Site Solar Array

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Rachel Williams on May 11, 2022, 11:02 am

I am working on a project that, through a series of contract issues during construction, does not have...

Last reply: Rachel Williams, May 11, 2022, 2:17 pm

CxA Qualification requirements

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Ryan Younis on Nov 11, 2019, 11:12 pm

Hello, 
i am looking to see if LEED requires any credentials specifically for the...

Last reply: Scott Bowman, Feb 28, 2020, 4:06 pm

Commissioning Documentation for 7 separate towers sharing a common ground floor & podium level with shared/mixed MEP Systems

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Joshua ADY on Mar 10, 2019, 6:24 am

We are working as an independent...

Last reply: Scott Bowman, Aug 11, 2019, 6:23 pm

Commissioning of Existing Equipment

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Jatuwat Varodompun on Jul 22, 2019, 1:24 am

We have a major renovation project which is 40% of gross area. Do we need to...

Last reply: Scott Bowman, Aug 11, 2019, 5:37 pm

All equipment tested as part of commissioning?

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Jill Watkins on Mar 22, 2019, 11:22 am

I am LEED consultant on a convention center renovation/addition and some team members are asking whether or not all equipment needs to be tested in all modes of operation, or if one of each type...

Last reply: Dave Hubka, Aug 5, 2019, 1:47 pm

Renewable Energy unable to be commissioned due to delays, can we still submit for LEED review?

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Rachel Manoguerra on Apr 30, 2019, 11:45 am

The project I am working on is "complete" and the owner wants to submit for final LEED review.  However, the PV has been delayed and not installed on the project. Therefore, as...

Last reply: Scott Bowman, May 25, 2019, 12:37 am

OPR and BOD documents

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Carlos Vazquez on Dec 1, 2017, 12:36 pm

I accepted an assignment of...

Last reply: emily reese moody, Oct 24, 2018, 4:17 pm