Process Energy for Manufacturing facility

NC-2009 EAp2:Minimum Energy Performance
posted by  Johnathan Woodside  on 

I have seen several posts pertaining to process energy and how it should be modeled, but I am still unclear as to how it should be treated pertaining to manufacturing process energy.

1
Thu May 3, 2012, 5:53 am

Separate Heating and Cooling Plants

General forums
posted by  James Del Monaco  on 

Our project is located on a University campus with two separate DES buildings. One DES building houses all the chilled water equipment including chillers, pumps, cooling towers, etc.

1
Mon Sep 10, 2012, 4:35 pm

eQuest for LEED Experience

NC-2009 EAp2:Minimum Energy Performance
posted by  Sam Watters   on 

Hello, My project team is looking into doing the energy modeling for a project in house, and I am wondering if anyone has a sense of how much experience is necessary to learn to use eQsuest softwa

1
Thu May 3, 2012, 5:59 am

Non-LEED Certifiable buildings definition?

General forums
posted by  Kerrie Kannberg  on 

Hi, In the MPR 2011 revisions there is mention of having a site boundary with either multiple LEED certifiable buildings within the boundary, thus using the AGMBC, or having Non-LEED Certifiable b

1
Mon Jun 25, 2012, 9:05 pm

IEQp1 ASHRAE 62MZ Calculator-Please Help

NC-2009 IEQp1:Minimum IAQ Performance
posted by  Helen Williams  on 

Help please! I have to submit the 62MZ Calcualtion today on a Storage Facility Project. IEQ Prereq 1 was denied and now in appeal.

1
Sat May 12, 2012, 3:43 pm

Roof or Non-roof?

CS-2009 SSc7.2:Heat Island Effect—Roof
posted by  Katherine Ann Resurreccion  on 

Hi All, We are working on a high-rise office project that will sit on top of an existing structure.

1
Tue May 8, 2012, 10:58 pm

Materials Reuse-Clarification of credit implementation

NC-2009 MRc3:Materials Reuse
posted by  Elle Brown  on 

Can some one clarify if I'm understanding the implementation of this credit correctly? If material is salvaged onsite it must be used in a purpose other than for which it was intended (except for

1
Thu May 3, 2012, 3:44 pm

LEED Boundary

General forums
posted by  Nanechka Pagan  on 

The project consist of the construction of a new middle school and the remodelation of the existing elementary school both will shared some areas like the existing parking and the electric substati

1
Wed Sep 5, 2012, 8:51 pm

Cutsheet Translation

CS-2009 WEp1:Water Use Reduction
posted by  Alessio Zampaglione  on 

Our project is In Italy and most of the cutsheets, certifications and declarations that we have are written in Italian and not in English.

1
Sun Sep 2, 2012, 2:07 pm

Landfill Generated Methane Gas

NC-2009 EAc2:On-Site Renewable Energy
posted by  Kendal Neitzke  on 

Our building project is a methane pumping facility located at landfill that is the source of the methane.

1
Thu May 3, 2012, 3:55 pm