Case 2. Demand response program not available (1 point)
CS-v4 EAc4:Demand responseposted by Ciaran McCabe on
Has anyone successfully used a Building Management System to achieve this credit where a program is not available. If you are you able to provide details of the system used. Thanks.
NC-v4.1 LTc8: Electric Vehicles
NC-v4.1 LTc8:Electric Vehiclesposted by Brian Johnson on
Hello, I have a question regarding the LTc8 Electric Vehicles credit. If our project only requires 2 parking spaces to have ESVE installed, does that mean each parking space must have an inde
Weather-Based Controls/ Moisture & Rain Sensors
NC-v4 WEp1:Outdoor water use reductionposted by LUCY WILLIAMS on
Hi All-
2020 SDL Winter Summit - A Few Spots Available!
posted by RoseAnn Grimes on
Hello everyone, Happy New Year!
Denied by not doing " use of ongoing feedback mechanisms ". How can we appeal?
CI-v4 IPc1:Integrative processposted by Jorng-ren Chern on
Our LEED ID+C V4 IP credit was denied and the following review comment was provided:
Site Selection and Energy-Related Systems
Energy Star Rated Power Value and Computation
CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliancesposted by Gene Harn Lim on
We are computing the Energy Star Equipment table and struggle to source the equipment's rated power. A few questions:
What is meant by Informal Transit?
CS-v4.1 LTc4:Surrounding Density and Diverse Usesposted by Amgad Khattab on
What is meant by "informal transit" in LEED v4.1?
Do Uber Bus, Careem Bus and Swevl qualify to achieving this option?
What is meant by Informal Transit?
CS-v4.1 LTc4:Surrounding Density and Diverse Usesposted by Amgad Khattab on
Project Zero Lot Line with Major Renovation
NC-v4 SSp1:Construction activity pollution preventionposted by Victoria Rios Esteve on
Hi everyone!
Still able to have commingled waste being recycle?
NC-v4 MRp2:Construction and demolition waste management planningposted by Victoria Rios Esteve on
Hi everyone!