LEED Interpretation 10372

NC-2009 MRc7:Certified Wood
posted by  Tristan Roberts  on 

I don't think the policy it gives is anything new—a lot of us have worked to choose to report wood content as either recycled or FSC, but not both—but FYI, LEED Interpretation 10372 was released on

2
Principal
Jason Grant Consulting
LEEDuser Expert
115 thumbs up
Mon Apr 7, 2014, 3:34 pm

LEED-NC or LEED-CI

LEED Rating System Selection
posted by  Samuel Nation  on 

We are renovating a large portion of a bldg on a University campus but there is a significant area of the building we are not touching at all. It was renovated a couple of years ago.

3
PE, LEED AP B D + C
DVPE
LEEDuser Basic Member
2 thumbs up
Mon Apr 7, 2014, 2:50 pm

Pressure Drop adustment in Section 14 Tables

NC-2009 EAp2:Minimum Energy Performance
posted by  Omar Elrawy  on 

Actually I'am not able to correlate section 14 required inputs under pressure drop column "CFMd", and the requirements of ASHRAE TABLE 6.5.3.1.1 B in (pascals/ in.w).

7
Green Building Consultant | Researcher
GreenA Consultants
LEEDuser Basic Member
38 thumbs up
Mon Apr 7, 2014, 2:31 pm

Option 3 Under LEED ND V4

ND-v2009 SLLc2:Brownfields redevelopment
posted by  Martine Desbois  on 

Could you please explain that Option. I am not sure I understand when it is applicable. Thank you OPTION 3.

3
Fri Apr 4, 2014, 5:23 pm

Clarification on prescriptive option skylight/floor area ratio

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Jason Levine  on 

We are in the process of completing the spreadsheet for credit IEQ 8.1 for a NC project. Kalwall skylights are being used, in addition to Solatube 330 DS daylighting systems.

4
CEO, former USGBC Faculty
Innovative Design, Inc.
LEEDuser Basic Member
8 thumbs up
Fri Apr 4, 2014, 3:53 pm

LEEDBoundary 100%parking bassement Not all levels to be included

LEED Guidance for Campuses and Multiple Buildings
posted by  Gabriela Hernández Castillo  on 

CAMPUS: Two office towers designed to meet LEED Core & Shell with three parking bassement levels, the parking structure occupies the 100% of the site, in addition there is a residential tower t

3
Fri Apr 4, 2014, 12:50 pm

Spaces left for future use should be simulated as conditionned?

NC-2009 EAp2:Minimum Energy Performance
posted by  Valentin Grimaud  on 

Dear community, I have a project where some spaces will be left for future use, while most of others are designed and built for immediate use.

2
Default Avatar
VP of Innovation
Sustainable Investment Group
LEEDuser Basic Member
110 thumbs up
Fri Apr 4, 2014, 10:02 am
4
Default Avatar
Principal : Energy / Electrical Engineer
BuildingPhysics South Africa
LEEDuser Basic Member
94 thumbs up
Fri Apr 4, 2014, 12:38 am

Audio Visual Equipment part of prerequisite?

CI-2009 EAp2:Minimum Energy Performance
posted by  Saju Varghese  on 

Does audio visual equipment need to be included into the appliances requirements including projectors, speakers, led display, interactive displays, etc?

5
Thu Apr 3, 2014, 11:08 pm

LEED baundary

CS-2009 PIf1:Minimum Program Requirements
posted by  gabriel Morales  on 

Our project is located in an area with 3 additional towers (one residential offices and 2), the parking lot of our office tower with LEED certification, has its parking in basements 3, 4 and 5, whi

3
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Thu Apr 3, 2014, 9:42 pm