Topic | Recent |
---|---|
Collocation data centerData-Centers-NC-v4 EAp2: Minimum Energy Performanceposted by Charalampos Giannikopoulos on Feb 18, 2014, 9:40 am
For a Collocation instead of an Enterprise Data Center, where the developer has no control over the servers to be installed, how would the servers be modeled? Last reply: Charalampos Giannikopoulos, Jul 16, 2014, 3:06 pm |
|
LEED EB O&M Certification- optimized energy performanceData-Centers-NC-v4 EAp2: Minimum Energy Performanceposted by satheesh M on Jul 3, 2014, 6:13 amMarcus Sheffer LEED Fellow 7group / Energy Opportunities LEEDuser Expert 5903 thumbs up July 9, 2014- 1:24 pm The questions should be posted to a different forum. Log in or register to post comments ... Last reply: Marcus Sheffer, Jul 9, 2014, 1:24 pm |
|
Baseline hvac system for data centerData-Centers-NC-v4 EAp2: Minimum Energy Performanceposted by Charalampos Giannikopoulos on Jul 3, 2014, 5:58 am
I'm trying to do my first model for a data center and looking at the table in appendix g of ashrae 90.1.2010 for the hvac system that I have to follow for the baseline model I can't understand if... Last reply: Marcus Sheffer, Jul 9, 2014, 1:22 pm |
|
Energy Modeling Procedure for a Data CenterData-Centers-NC-v4 EAp2: Minimum Energy Performanceposted by Santiago Rodriguez on May 30, 2014, 3:21 pm
We are working on a project that is seeking the LEED NC 2009 Certification. The project is a data center so we are using the Minimum Energy Performance Data Center Calculator spreadsheet in order... Last reply: Marcus Sheffer, Jul 9, 2014, 12:18 pm |