Forum quick links
Buildings Connected by Maintenance Tunnel
posted by Dave Wortman on
I am working on a project where two buildings directly adjacent to each other but separated by 10-20 feet are being designed to be connected by an underground tunnel.
Densely occupied spaces exemption
EBOM-2009 IEQc1.2:IAQ Best Management Practices—Outdoor Air Delivery Monitoringposted by Katherine Ann Resurreccion on
Hi All, We have a project that has a lot of meeting rooms (area of each room is smaller than 150 square feet) that can accomodate 4 person per meeting room - therefore considered densely occupied
ENERGY COST BUDGET METHOD, ENVELOPE
CI-2009 EAp2:Minimum Energy Performanceposted by TOMAS URIBE on
Greetings. I am working on a Commercial interior project pursuing the EAP2, and I chose the section 11 as an alternative to prescriptive approach, but, i am a little bit confused about how to sim
Concept Designers as CxA?
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Ward Miller on
The project in question is a design and build project for which the general contractor will be assigned the project's design and construction activities; however, there is an architectural and engi
Can AE-1 be CxA?
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by ANNE JURAN on
We prepared the RFP (or bridging documents) for a design-build project.
Compliance?
CI-2009 EAp2:Minimum Energy Performanceposted by Alex AC on
Hi LEEDuser community, I have read some old posts regarding this issue, but I still want to double check with you guys. I hope you don´t mind.
DES: virtual rate and efficiency
CS-2009 EAp2:Minimum Energy Performanceposted by FABIO VIERO on
Hello all, according to the document “Treatment of District or Campus Thermal Energy in LEED V2 and LEED 2009 – Design & Construction”, for Option1: Virtual District Hot Water Rate [$/MBTU] =
single stream recycling
EBOM-2009 MRc6:Solid Waste Management—Waste Stream Auditposted by Courtney Royal on
Our project is located in Ithaca, NY and curbside recycling pickup has moved into a single stream recycling collection.
Green Roof modeling for EAc1
NC-2009 EAc1:Optimize Energy Performanceposted by Kalyan Nishtala on
Hi All, I am modeling a 350,000 sqft dormitory/dining hall located in NY. Part of the roof of this building green roof (approximately 10%).
Establishing baseline system
NC-2009 EAc1:Optimize Energy Performanceposted by Kari Krolikowski on
My project consists of the following types of spaces: 1. Office: 2,300 SF 2. Manufacturing / laboratory: 24,055 SF 3. Warehouse: 26,905 SF 4.