Forum quick links
Typo in DES v2?
NC-2009 EAp2:Minimum Energy Performanceposted by Haojie Wang on
To calculate the virtual rate, DES v2 option 1 2.4.2.1 gives the equation of $/MBTU of hot water = 1.59*$/MBTU fuel + 3 * $/kWh electricity. This would gives me a really big number.
ASHRAE 90.1-2007: 6.4.3.4.2 building height exemption
CI-2009 EAp2:Minimum Energy Performanceposted by André Harms on
The client of an commercial interiors project location wants to avoid the use of motorized dampers where possible.
Meeting 20% with no Operational Activity
EBOM-2009 SSc2:Building Exterior and Hardscape Management Planposted by Michelle Rosenberger on
What do I do with the snow and ice removal activity during the performance period if we don't get any snow? It appears the requirement is 20% compliance in each operational area.
Wood wallbase
NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systemsposted by Devani PERERA on
Has anyone seen a floorscore for wood wall base? We have awood wallbase that is manufactured by the millwork contractor.
Transitional Entry Atrium Lobby belong in Energy Model?
NC-2009 EAp2:Minimum Energy Performanceposted by Joyce Kelly on
A five story Atrium is being constructed in a science building. It is also the main entry into the building and furnished with benches for transient use.
Option 3
NC-2009 IEQc8.1:Daylight and Views—Daylightposted by Mike D on
For option 3, do measurements have to be taken more than once?
Option 3 daylight measurement
NC-2009 IEQc8.1:Daylight and Views—Daylightposted by Stella Stella on
Hi, We are proposing to carry out the Option-3 daylight measurement in our project to demonstrate compliance.
Level of Participation by Enhanced CxA in Fundamental Cx Tasks
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Annalise Reichert on
We are currently working on a project where an independent third party was contracted to perform Enhanced Commissioning tasks, and a disinterested employee of the General Contractor performed Funda
Regularly Occupied Space
EBOM-2009 PIf3:Occupant and Usage Dataposted by Saul Pichardo, AIA on
Hello, Where can I find information on what is considered "regularly occupied space" in a warehouse facility that has most of its space dedicated to product storage and much of the open area used
Shade from trees outside of site
NC-2009 SSc7.1:Heat Island Effect—Non-Roofposted by Summer Gorder on
Can the shade from tree canopy include trees that are outside of the project boundary?