FAQs about EAp2 :

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Project self shading for separate certifications

We have a project that is one large structure comprised of a rail station that acts as a platform on top of which two towers sit. It is technically one structure, but the 3 pieces are 3 separate LEED projects. My question is whether the shading from the 2 other pieces can be included in the proposed energy model without including it in the baseline. Since they are highly dependent on one another, removing the adjacent buildings could result in lots of proposed unmet hours. Technically i think it should be considered as if it is one building that is allowed to self-shade in the proposed; however, it is 3 separate projects with respect to LEED.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 06/10/2015 - 17:36

Why is it one building but 3 LEED certifications? Do they have separate HVAC systems? How are you preparing the model(s)? All one model with meters or three separate models? If indeed they are separate I would suggest that since you cannot model adjacent buildings you can't in this case either.

Wed, 06/10/2015 - 17:48

It is probably more correct to say it is one structure (http://www.som.com/projects/all_aboard_florida). They are separate systems. We have 3 models with the other pieces modeled as adjacent buildings.

Wed, 06/10/2015 - 21:24

The other buildings are adjacent buildings and should not be included in the models according to the rules of 2007. In 90.1-2010 the rules change so if you can find an addendum that changed it maybe you could use it. I am not sure if that change was via addendum or not.

Wed, 06/10/2015 - 17:56

It is my understanding that there is an addendum for that change, but it forces you to also include the adjacent buildings in the baseline. Seems like that is what we will have to do; otherwise, the performance of the design won't be accurately represented. Thanks