Forum quick links
Cold Climate
NC-2009 SSc7.2:Heat Island Effect—Roofposted by Erin Holdenried on
Does anybody have experience using an alternate compliance path for a project in a cold climate?
Baseline for Cold Storage project
NC-2009 EAp2:Minimum Energy Performanceposted by Thu Nguyen on
Hi all experts, My project in Vietnam with major function is Cold Storage, with operational temperature would be -25 degree. Currently, we concern for BASELINE OF ENERGY MODEL.
Single Tenant building, no parking
CI-2009 SSc3.3:Alternative Transportation—Parking Availabilityposted by J Villa on
I am working on a CI project that is located in a single tenant building that has an area more than 75% of the total building area. The building has no parking and none is subsidized.
How to implement WELL in a partially occupied building...?
posted by Brian Salazar on
Hello! First, thank you Tristan for adding a WELL discussion to this site. I'm sure it will be a great resource for a whole host of "do gooders" like myself.
Athletic Field Definition
NC-v4 WEc1:Outdoor water use reductionposted by Michelle DiPenti on
Our project has an outdoor area, as a part of the sports medicine department, which patients will use to do sprints, drills, and other exercises.
Comprehensive transportation management plan - behavioral change
NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Anna Korinkova on
We are pursuing the Exemplary performance option for SSc4.2 - the development of a comprehensive transportation management plan.
Leed v4- NC of Logistic Center.
NC-v4 EAp2:Minimum energy performanceposted by Helena Garcia on
It is making energy simulation for a logistic center for storage. Local regulations based on European regulations not required to be heated, instead ASHRAE required to be heated. How should we co
building area method
NC-2009 EAp2:Minimum Energy Performanceposted by Francesco Passerini on
Two issues regarding the building area method. 1.
Initial fit-out vs alteration
CI-2009 PIf2:Project Summary Detailsposted by Kate Bubriski on
I have a project that is a tenant fit-out in an existing building.