Interpretation for Underground Stormwater Retaining System
NC-2009 SSc5.1:Site Development—Protect or Restore Habitatposted by Candice Rogers on
Good morning - We have a project that is greenfield.
Painting or Coating for Steel Structure
CS-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Ali Soufan on
Hi In a steel structure building, in which the steel is within the building weather proof, two applications are applied: 1- Fire Proof Paint (applied on site) 2- Solvent Based Top Coat Paint (appli
SS PC27 - a short feedback
CS-2009 IDc1:Innovation in Designposted by Elodie DUMAS on
Dear all, A short feedback about our experience concerning LEED SS PC 27 use for a major refurbishment office project in France, under LEED for Core an Shell version 3. This Pilot Credit was aim
Coco, Coir, or other fiber mats
NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systemsposted by Erica Downs on
Anyone have experience with how to treat coco fiber mats?
Smoke-free Campus
NC-2009 IEQp2:Environmental Tobacco Smoke (ETS) Controlposted by Kim Wajda on
The project in question is part of a high school campus with a strict campus-wide smoke-free policy.
Co-working space
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Gustavo De las Heras Izquierdo on
Hallo, My project is a co-working space for multiple companies. The tenants won't be assigned a fixed space to work in, and there are common spaces where anyone can sit down and work.
Permanent Exhibit Vs Temporary Exhibit
NC-2009 IEQc4.4:Low-Emitting Materials—Composite Wood and Agrifiber Productsposted by Ralph Bicknese on
Hello, This question is also related to any interior LEED credit. We are designing an exhibition space for a museum. This exhibition space has Temporary and Permanent Exhibitions.
Calculating material use for mock-ups.
NC-2009 MRc4:Recycled Contentposted by Peter Doo on
When working on large projects with substantial mock-ups, should one include these materials in the project documentation?
Determining site area on lot with multiple buidings
Mid-Rise-v4 SSc2:Rainwater managementposted by Phil Vanderloo on
Can someone help me with how to determine the total site area for calculations on a lot with an existing residence, and a future LEED certified accessory dwelling.
Does a Party wall count for the Window to wall ratio?
NC-2009 EAp2:Minimum Energy Performanceposted by Zonda E. Team on
Hi there, Im modelling a corner building, which has two adjacent buildings so only the façades facing the street are in contact with the exterior environment.