Basline system for 5 floors + small below grade conditioned spac

NC-2009 EAp2:Minimum Energy Performance
posted by  Zonda E. Team  on 

What is in your opinion the baseline for the following building: Floor area:12,000 sqm (130,000 sqft) Floors: 5 above grade, mostly conditioned.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Sat Jul 4, 2015, 7:31 pm

Pre-development Conditions

NC-2009 SSc6.1:Stormwater Design—Quantity Control
posted by  Leandro Silva  on 

Greetings Our project is a 30 year old building undergoing a Major Renovation and will be registered as LEED-NC v2009. In calculating pre- and post-development runoff, do we consider the pre-develo

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Fri Jul 3, 2015, 6:26 pm
6
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Fri Jul 3, 2015, 6:18 pm

SS 4.4 No New Parking.

NC-2009 SSc4.4:Alternative Transportation—Parking Capacity
posted by  Rezkar Abdulmajeed  on 

I have the first LEED project in a campus. The project will be built on an existing parking lot and no new parking will be added within the LEED project boundary.

5
Fri Jul 3, 2015, 2:16 pm

Fuel Stations for Shared Parking Lot Outside of LEED Boundary

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Mary Kay  on 

Our project has no new parking. We are on a campus where there is an existing parking lot adjacent to our building, but not within our LEED project boundary.

2
President
HJKessler Associates
LEEDuser Basic Member
41 thumbs up
Fri Jul 3, 2015, 1:39 pm

Additional lighting power density in a retail store

CS-2009 EAp2:Minimum Energy Performance
posted by  Felipe Duran  on 

Dear All, We are working on a shopping mall project which is pursuing LEED for C&S certification.

3
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jul 2, 2015, 9:05 pm

Shared building electricity meter

EBOM-v4 EAp2:Minimum energy performance
posted by  LEED Pro Consultant  on 

We have a building which shares electricity meter with an adjacent building, only one building will be intended for certification, it is possible to identify the percentage of consumption in every

2
Senior Sustainability Manager
WSP - Built Ecology
LEEDuser Expert
188 thumbs up
Thu Jul 2, 2015, 8:39 pm

small DES

NC-2009 EAp2:Minimum Energy Performance
posted by  Francesco Passerini  on 

For a preliminary review I modeled a building that is heated and cooled by four geothermal heat pumps that are located in a technical room within the building.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jul 2, 2015, 2:57 pm

Pilot Credit Closed

Pilot-Credits EApc8:Demand response
posted by  Haley Duncan  on 

Hi, It looks like USGBC has closed this pilot credit to NC 2009 projects.

2
Sr. Electrical Engineer
Integrated Design Solutions
LEEDuser Expert
516 thumbs up
Thu Jul 2, 2015, 1:40 pm

Historical data for an International Convention Centre

Calculating FTEs
posted by  Meghan Ward  on 

Where could we access historical data on occupancy or attendance data of an international convention centre? Would anyone be able to provide a some guidance on calculating FTEs and transients for a