LEED project boundary

CS-v4 MPR2:Must use reasonable LEED boundaries
posted by  Francesco Passerini  on 

The site area of our project has some differences between ground floor and the basement: the basement area is higher than the ground floor area.

3
Wed Apr 9, 2025, 2:58 pm
4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Apr 9, 2025, 2:58 pm

MRpc103 - Integrative Analysis of Building Materials in NC 2009

NC-2009 IDc1:Innovation in Design
posted by  Sara Goenner Curlee  on 

I recently completed the work effort for MRpc103 - Integrative Analysis of Building Materials for a v4 project, and had a v2009 project with an open innovation credit.&nbs

3
Tue Apr 8, 2025, 9:38 pm

Helpful links to complete Site Assessment worksheet

NC-v4.1 SSc1:Site Assessment
posted by  Micah McLain  on 

Which websites do you all use to complete your Site Assessment worksheets for US-based projects?

3
Default Avatar
Sustainable Design Director
Bell Architects
LEEDuser Premium Member
40 thumbs up
Mon Apr 7, 2025, 6:39 pm
2
LEED AP-ND, Principal
Criterion Planners
LEEDuser Expert
231 thumbs up
Mon Jul 7, 2025, 5:05 am
5
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Mon Apr 7, 2025, 2:45 pm

Land clearing debris

NC-2009 MRc2:Construction Waste Management
posted by  Kelly Humphry  on 

I understand that LEED does not count land clearing debris in its construction waste recycling numbers, however, it also does say in the manual that "any construction debris processed into a recycl

2
Default Avatar
Architect, LEED Consultant
Polk Stanley Wilcox Architects
LEEDuser Basic Member
29 thumbs up
Mon Apr 7, 2025, 9:14 am
2
LEED AP-ND, Principal
Criterion Planners
LEEDuser Expert
231 thumbs up
Mon Apr 7, 2025, 8:17 am

Welcome to the LEEDuser job board

Help Wanted: LEED-related Jobs
posted by  Paula Melton  on 

Hi! This job board is a new feature we're trying out here at LEEDuser.

29
Sun Apr 6, 2025, 8:47 pm

Prescriptive Compliance - Documentation?

CI-v4.1 EAp2:Minimum Energy Performance
posted by  Edgar Arevalo  on 

So how should one pursue the prescriptive method for this prerequisite?  In the sample form, it says to provide documentation demonstrating compliance with ASHRAE 90.1-2016, Sections 5 though

8
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Sep 25, 2025, 6:25 am