Proper way to apply ASHRAE 62.1 to baseline model?Schools-2009 EAp2: Minimum Energy Performanceposted by Joseph Lewis on Nov 13, 2013, 1:59 pm
I have a project where the proposed design has demand controled ventilation. I modeled the... Last reply: Marcus Sheffer, Dec 4, 2013, 8:14 am |
|
EAp2Schools-2009 EAp2: Minimum Energy Performanceposted by Ema S on Jun 20, 2013, 5:34 pm
Does anyone out there know what the following comment pertains to: Last reply: Marcus Sheffer, Aug 28, 2013, 12:45 pm |
|
HAP v4.5 and Hot Water Supply Temperarture ResetSchools-2009 EAp2: Minimum Energy Performanceposted by Matt Humphreys on Aug 28, 2013, 11:53 am
HAP version 4.5 is not capable of modeling hot water temperature supply temperature reset in the baseline case as required under ASHRAE 90.1-2007 Appendix G3.1.3.4 yet the software has been... Last reply: Marcus Sheffer, Aug 28, 2013, 12:41 pm |
|
Does anyone out there knowSchools-2009 EAp2: Minimum Energy Performanceposted by Ema S on Jun 20, 2013, 5:34 pm
Does anyone out there know what the following comment pertains to: |
|
Multiple Building-Energy CreditsSchools-2009 EAp2: Minimum Energy Performanceposted by Ameet AA on Nov 6, 2012, 6:09 amcan be provided in a forum like this and I am not intimately familiar with IES. In eQUEST we would likely just create separate meters for each building within a single model. But that would also depend... Last reply: Christopher Schaffner, Dec 27, 2012, 2:21 pm |
|
EPA Target Finder rating toolSchools-2009 EAp2: Minimum Energy Performanceposted by Ameet AA on Dec 3, 2012, 9:28 am
Following requirement is stated even in the LEED 2009 School Alternative compliances path for project outside the U.S.(July 2012) "The project must establish an energy performance rating... Last reply: Marcus Sheffer, Dec 3, 2012, 12:17 pm |
|
deleteSchools-2009 EAp2: Minimum Energy Performanceposted by Jean Marais on Nov 20, 2012, 4:06 pm
delete |
|
Addition to existing buildingSchools-2009 EAp2: Minimum Energy Performanceposted by mital patel on Jul 30, 2012, 12:34 pm
We have a existing building that is LEED Silver and we are adding to same building. New addition is also LEED Silver. Do I need to model both existing and new addition or only new addition. I... Last reply: Marcus Sheffer, Jul 30, 2012, 1:13 pm |
|
The baseline U-valuesSchools-2009 EAp2: Minimum Energy Performanceposted by Ameet AA on Apr 13, 2012, 5:24 am
The baseline U-values proposed by ASHRAE 90.1-2007 for a building with high thermal mass in climate zone 1 (see below extracted from table 5.5-1) seem to be too low-performing. Are these correct... Last reply: Ameet AA, Apr 27, 2012, 7:33 am |
|
Renewable Energy Source SummarySchools-2009 EAp2: Minimum Energy Performanceposted by Sara Goenner Curlee on Apr 9, 2012, 2:30 pm
I'd like to understand better how to input what is needed in Table L-1 for our solar thermal system (our solar PV system was easy to input). The system designers say the annual production is 9.4... Last reply: Marcus Sheffer, Apr 11, 2012, 2:29 pm |