Sprayed concrete as a temporary stabilization measureCS-2009 SSp1: Construction Activity Pollution Preventionposted by Michael E. Edmonds-Bauer on Dec 17, 2012, 11:05 am
Our project has around 10 levels of undergrouns parking. A huge ramp for earth-movement vehicles is being created as construction evolves. The slopes at the sides of the ramp go for more... Last reply: Mauricio Ramirez, Mar 6, 2019, 8:32 pm |
|
Guidelines/Sample of a good ESC plan proposalCS-2009 SSp1: Construction Activity Pollution Preventionposted by Ann E on Jul 10, 2018, 11:06 am
Hi, Last reply: David Eldridge, Jul 11, 2018, 4:57 pm |
|
Final stabilization for zero-lot line projectsCS-2009 SSp1: Construction Activity Pollution Preventionposted by Gabriela Hernández Castillo on Dec 26, 2010, 8:32 pm
For projects that use all site for construction, how does the... Last reply: Ward Miller, Feb 12, 2018, 4:37 am |
|
2012 EPA CGP comply with this prerequisite?CS-2009 SSp1: Construction Activity Pollution Preventionposted by Pamela Svetllana Santos Souza on Jul 14, 2017, 7:13 am
I'm modelling for LEED C&S 2009 and the project has 26 floor type of mixed-use offices. Does the 2012 EPA... Last reply: Tristan Roberts, Aug 26, 2017, 6:10 pm |
|
v6 Forms with Different Compliance PathsCS-2009 SSp1: Construction Activity Pollution Preventionposted by Michelle Rosenberger on Dec 12, 2016, 5:02 pm
This prerequisite has always had 3 compliance paths - photos, inspection reports or a maintenance narrative. The v6 form for this prerequisite apparently only has two compliance paths - photos or... Last reply: Michelle Rosenberger, Dec 21, 2016, 2:35 pm |
|
Precertification- LEED 2009 Core & ShellCS-2009 SSp1: Construction Activity Pollution Preventionposted by Michael Heacock on Nov 1, 2016, 8:36 pm
We are working on submitting a precertification. I'd thought the credits team was working on were design phase. If I submit the precertification, can I quickly turn in for design phase. I've read... |
|
In which construction phase can I certify my building?CS-2009 SSp1: Construction Activity Pollution Preventionposted by Hazem Yusuf on May 3, 2014, 12:10 pm
Construction phase of an office building is consisting of multi stages. Those stages are including but not limited to; excavation stage, concrete skeleton stage, block work and plastering stage,... Last reply: Tristan Roberts, Nov 27, 2015, 5:06 pm |
|
Fire during constructionCS-2009 SSp1: Construction Activity Pollution Preventionposted by Constanza Cattan on Dec 23, 2014, 9:03 am
Dear all, Last reply: Tristan Roberts, Dec 23, 2014, 12:01 pm |
|
SSp1 description for CS precertificationCS-2009 SSp1: Construction Activity Pollution Preventionposted by Nándor Kovács on Aug 18, 2014, 7:55 am
We are working on a project precertification (v2009) and I was suprised that the precertification credit form requires a description of measures that will be implemented at the project site.... Last reply: Michael DeVuono, Aug 18, 2014, 7:58 am |
|
NYC projectCS-2009 SSp1: Construction Activity Pollution Preventionposted by Megan Bove on May 27, 2014, 11:02 am
Hi. I have a project in the city where subway grates are found right outside the project fence as well as always a storm drain that is on a very busy street. Are these required to be covered and/... Last reply: Michael DeVuono, May 27, 2014, 11:42 am |