Forum quick links
Percent of Occupants with access to the fixture.
CS-2009 WEp1:Water use reductionposted by Guillermo Hernandez Espinoza on
Hello everyone.
I'm a bit confused with the Percent of Occupants calculation on the Water Use Reduction Calculator.
HVAC system selection for unfinished spaces.
CI-v4 EAp2:Minimum energy performanceposted by Graham Langton on
I have a a single story building that requires a Baseline system 6 (per table G3.1.1A), which according to G3.1.1 is modeled on a floor by floor basis - So I have 1 system.
Testing Procedure
Pilot-Credits EQpc57:Enhanced acoustical performance - exterior noise controlposted by Margaret Hamilton on
We're pursuing this pilot credit for a project in the UK.
Lighting Power Density for sauna
NC-v4 EAp2:Minimum energy performanceposted by Francesco Passerini on
What shall I consider as Lighting Power Density (TABLE 9.6.1 of ASHRAE 90.1-2010) for a sauna that is inside a hotel?
Best Regards
Tenant Guidelines credit substitution to v4?
CS-2009 SSc9:Tenant design and construction guidelinesposted by Maria Porter on
Now that Tenant Guidelines in v2009 are a bit dated, I’m referring to that CI v2009 no longer exists for new projects, wouldn’t it make more sense to use v4 credit requirements instead?
Associated Grounds Metering
NC-v4 WEp3:Building-level water meteringposted by Nathan Gauthier on
We got a response back from GBCI today for WEp3 after asking about the metering requirement for the "associated grounds".
Shared Landscape
CS-v4 WEp3:Building-level water meteringposted by Ricardo Sá on
Dear All,
One of our clients is developing a project that includes two buildings (9 levels office tower and a retail building) sharing a common landscape area.
Open space 30% requirement at Ground Level only?
NC-v4 SSc3:Open spaceposted by Susan Di Giulio on
Can you include open spaces at roof level (Green roof, accessible by all) as part of the 30% requirement, or does the entire 30% need to come from open space at ground level only?
IAQ Testing
NC-v4 EQc4:Indoor air quality assessmentposted by Shannon Oletic on
Following Option 2 of this credit, is it acceptable that sampling areas of the building are tested once construction has finished in that area even if construction has not finished in other parts o