Recommissioning vs Commissioning experience for CxA

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Dustin Campbell  on 

We would like to get a comment from someone that has had experience with this: When selecting a CxA, would someone that has eperience on 2 or more projects as the "Recommissiong Authority" be suff

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Fri Mar 11, 2011, 12:48 pm

double counting 7.1 and 7.2?

NC-2009 SSc7.1:Heat Island Effect—Non-Roof
posted by  Christopher Sawyer  on 

My project is a bus maintaince depot in New York City with a zero lot line. The top floor (under the "roof" is all bus parking for vehicle maintenance and storage).

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Thu Mar 10, 2011, 11:25 pm

A person who is responsible for the thermal comfort?

NC-2009 IEQc6.2:Controllability of Systems—Thermal Comfort
posted by  Mathilda Jonsson  on 

In the project I'm working at there are seperate office spaces.

3
Green Certification Coordinator
Skanska Sweden
LEEDuser Basic Member
20 thumbs up
Thu Mar 10, 2011, 6:44 pm

Custom Built Salvaged Wood Furniture

CI-2009 MRc3.2:Materials Reuse—Furniture and Furnishings
posted by  Max Calabro  on 

I'm working on a restaurant, and we're having our dining tables custom built from salvaged wood.

3
Wed Mar 9, 2011, 11:39 pm

Louver Vents

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Biagio Arevalo  on 

Does anyone know if for the prescriptive path the light that passes through lovers count?

2
Wed Mar 9, 2011, 12:21 am

LT, VLT & Tvis

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Biagio Arevalo  on 

I´m planning to approach this credit through the prescriptive path but I´ve been having some difficulties finding the Tvis for the glass.

2
Wed Mar 9, 2011, 12:19 am

Occupant "Eco-involvement"

CS-2009 IDc1:Innovation in Design
posted by  Julien Daclin  on 

On a french project, the future occupants will be involved in the best practice functionning of the building. When external conditions are satisfying (temperature and wind) LCD screens placed in th

4
Head of Sustainability
Deerns France
LEEDuser Basic Member
24 thumbs up
Tue Mar 8, 2011, 10:50 am

Limiting access once the building is enclosed

NC-2009 IEQc3.1:Construction IAQ Management Plan—During Construction
posted by  Vanessa Seibert  on 

Our experience on projects is that limiting the access to one door with a long, regularly cleaned carpet, is expected by the LEED reviewer.

2
Director of Operations
Transwestern Sustainability Services
LEEDuser Basic Member
355 thumbs up
Mon Mar 7, 2011, 10:52 pm

Exhausted heat

NC-2009 EAc1:Optimize Energy Performance
posted by  Kath Williams  on 

Can a LEED project use exhausted/waste heat (and claim credit of some kind) from an adjacent building that is not being included in LEED project boundary?

2
Director of Operations
Transwestern Sustainability Services
LEEDuser Basic Member
355 thumbs up
Mon Mar 7, 2011, 9:33 pm

Systems Furniture Panel Fabric

CI-2009 IEQc4.5:Low-Emitting Materials—Systems Furniture and Seating
posted by  Lori Selcer  on 

We have specified panel sysems for our project which are Greenguard certified. However we are using COM fabric for the panels, that is, we are using fabric from another manufacturer.

5
Independent consultant on VOC issues
formerly with Eurofins Product Testing A/S
LEEDuser Basic Member
246 thumbs up
Sat Mar 5, 2011, 1:54 pm