MPR point 6 - Option 2 - Approved Format
NC-2009 PIf1:Minimum Program Requirementsposted by Sustentator Argentina on
Does someone know what is the other approved format (not energy star) for uploading consumption information?
LEED for Schools, Multiple Buildings
NC-2009 PIf1:Minimum Program Requirementsposted by Eric Bosley on
Hello All, I wanted to know if you have to use LEED Campus guidance for a LEED for schools project with multiple buildings.
Permanently-installed NOT compliant
EBOM-2009 IEQc3.5:Green Cleaning—Indoor Chemical and Pollutant Source Controlposted by SIG - Sustainability Main Account on
Based on comments on this forum, I assumed it was okay to permanently install walk-off material.
ASHRAE 90.1-2007 6.4.1.4 - Verification of Equipment Efficiences
NC-2009 EAp2:Minimum Energy Performanceposted by Marina Andrade on
There is a Brazilian HVAC manufacturer that has an centrifugal chiller with magnetic bearings equipment (air condensation).
COC Certification Required for GC...?
NC-2009 MRc7:Certified Woodposted by Adrienne Lynn on
We are a General Contractor and we are wondering if we, ourselves, would be required to get COC Certified when attempting to achieve MRc7? We purchase FSC plywood, dimensional lumber, etc.
Prerequisite IEQ 1
NC-2009 IEQp1:Minimum IAQ Performanceposted by Caro Wilbanks on
For specification section 230593 Testing, Adjusting, and Balancing for HVAC the architect is asking for a Air Balance Report for Prerequisite IEQ 1: Documentation of work performed for ASHRAE 62.1,
EP
CS-2009 EAc6:Green Powerposted by Mathilda Jonsson on
Hi I would like a clearifying how we get the exemplary performance credit for EAc6.
Data Center Rating System
NC-2009 PIf1:Minimum Program Requirementsposted by David Edenburn on
There are a lot of new data centers being built. My first reaction is to register these as C&S since they are providing rental space (the empty data "suites") to tenants.
shop applied paints?
NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Erin Holdenried on
Do factory applied paints need to comply with the VOC limits? Or only paints and coatings that are applied on-site?
Rebar Bonding Agent
NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Harvard University Green Building Services on
After searching through the comments and the SCAQMD standard itself and not finding a similar request/answer, I would ask what standard would a bonding agent used to connect rebar to concrete would