NC-2009 SSc6.2:Stormwater Design—Quality Controlposted by Albert Sagrera on
Hi, in our project we have a 60% of the site vegetated, planted with meadow, we have a small impervious surface near the building, and the building itself.
Apartment/Dorm
NC-2009 IEQc6.1:Controllability of Systems—Lightingposted by Tommy Linstroth on
Reading the guidance and from past projects its always been pretty straightforward for showing compliance with an apartment or dorm when every room has an on/off switch.
counting "individual" spaces
NC-2009 IEQc6.2:Controllability of Systems—Thermal Comfortposted by Erica Downs on
Would a private 2-person office count as one space or 2 when calculating the 50%?
Filtration during construction ( MERV 8)
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Sharon Morris on
I am currently working on a project that has a dual HVAC system. A Daikin mini split ductless system and a DOAS Desert Eir system with ducts & filtration.
Large Process Loads from Data Center in Office building
NC-2009 EAp2:Minimum Energy Performanceposted by Therese Malm on
We are working with a building where 60% of the annual energy use accounts for process energy due to a large data center.
process load
NC-2009 EAp2:Minimum Energy Performanceposted by HOUCINE TLEMSANI on
We are having the same problem working on a building where 48% of the annual energy usage is process load from computers, screens and tv’s.
Concrete Sealer
NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systemsposted by Allen Cornett on
Under Option 1 Table IEQc4.3-1 in the online form list "FloorScore" as the reference standard for "Sealer: Waterproofing, Concrete/Masonry", while it list "SCAQMD Rule 113" as the reference standar
Mineral-based finished flooring products
NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systemsposted by Allen Cornett on
In an addenda issued on 4/14/10 the followimg is stated, “Mineral-based finish flooring products such as tile, masonry, terrazzo, and cut stone without integral organic-based coatings and sealants
Mock up Room Waste Management
NC-2009 MRc2:Construction Waste Managementposted by John Covello on
Hi All, Our site is starting off with a mock up guest room villa as a test bed before we construct the balance of 90 odd guest villas.
MPR for adjacent buildings
NC-2009 EAp2:Minimum Energy Performanceposted by Francesco Passerini on
LEED project boundary lines that “slice” through party walls must not pass through any MEP service infrastructure.