NC-2009 EAc5:Measurement and Verificationposted by Gustav Alfaro on
Hi to all: Please help me to clarify how the baseline model is defined for the M&V plan, it is clear that for the "actual case" the proposed model created for the EAc1 must be calibrated based
LEED Interpretation #10134 as applied to fan coils
CI-2009 EAc1.3:Optimize Energy Performance—HVACposted by Silvia Ruiz on
Hi, Would a project be eligible to apply for this credit if the scope of work includes the provision and installation of 100% of the fan coils serving the certifiable space, even if they don't ha
EP Confusion re: SS C3.1,.3.2, and 3.3
CI-2009 SSc3.1:Credit Alternative Transportation—Public Transportation Accessposted by Elizabeth Ingram on
Hi Tristan! I am studying for the LEED 2009 ID+C and am confused regarding the graphics for the above credits and the way the EP is mentioned. They seem to differ.
LEED 2009 ID+C Study Guide Typo? IEQ C2
CI-2009 IEQc2:Increased Ventlilationposted by Elizabeth Ingram on
Hi! The above lists IEQ C2 as 5 points. Am I misunderstanding this? Is it another strange and wondrous EP or ID credit, or suite of credits?
Tenant spaces Completion
NC-2009 MPR2:Must be a complete, permanent building or spaceposted by Joel Cheely on
We are renovating urban buildings into apartments and speculative retail/commercial space. Some of the retail/commercial space will be constructed prior to application and some won't.
Can a credit in one rating system be considered ID in another?
NC-2009 IDc1:Innovation in Designposted by Stantec BG+LU FW on
Can a credit that occurs in one rating system be considered an ID credit in another rating system if there is no equivalent credit? The example: I am using LEED – NC.
Submeter for process uses
CI-2009 EAc3:Measurement and Verificationposted by Shoko Yasuda on
Hello, I am doing CI Retail project (LEED-CI 2009 EAc3 Case 1) and it includes dish washer and ice cube machine. I understand that we have to have sub meters for process loads.
Compliance Path Questions
Healthcare-v2009 IEQc4:Low-emitting materialsposted by Catherine Blakemore on
For each Group, do all products listed have to follow either Path 1 or Path 2? For eample Group 3 offers: Path 1.
High bay Areas LPD
NC-2009 EAp2:Minimum Energy Performanceposted by Saju Varghese on
We are working on a project with a bus repair bay areas for which we considered as "High Bay" areas for the energy model due to the fact that these areas are higher than 25 ft.
more than 1 system to simulate baseline building?
NC-2009 EAc1:Optimize Energy Performanceposted by jaume balana on
Hello, Our project is a two floors and 1300 m2 building, opened to four orientations.