No Smoking Signs

NC-2009 IEQp2:Environmental Tobacco Smoke (ETS) Control
posted by  Crissy Tsai  on 

Where do the no smoking signs need to be located? All exterior doors? Only ingress doors? Thanks, Crissy

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Mon Aug 5, 2013, 1:03 pm

ASHRAE Manditory Requirements Insulation

NC-2009 EAp2:Minimum Energy Performance
posted by  John Covello  on 

Hello, Is there a guide or list somewhere as to what materials are acceptable to use for insulation? We want to know what options we can use. Thanks. John

2
Default Avatar
Senior Sustainability Manager
UL Solutions
LEEDuser Premium Member
7 thumbs up
Sun Aug 4, 2013, 10:50 pm
2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Sun Aug 4, 2013, 9:24 pm

Hydroseeding

NC-2009 SSc5.1:Site Development—Protect or Restore Habitat
posted by  JOSE R. TAGLE  on 

I have a Project that is considering “Hydroseeding” as a permanent landscape design.

2
Default Avatar
Sustainability Architect
LEEDuser Basic Member
88 thumbs up
Fri Aug 2, 2013, 9:08 pm

Malfunctioning Water Meters

EBOM-2009 WEc1:Water Performance Measurement
posted by  Edward Malesevich  on 

Our project team is attempting the whole building metering along with the submetering option.

2
Project Director
WSP USA
LEEDuser Basic Member
381 thumbs up
Fri Aug 2, 2013, 7:37 pm

Parking under building - still need SRI ?

EBOM-2009 SSc7.1:Heat Island Reduction—Nonroof
posted by  Jaida Anderson-Lozano  on 

My project is currently assessing which credits for EBOMv2009 can be achievable by reviewing the LEEDonline forms. For credit SSc7.1 the project will achieve compliance via Option 2.

2
Sustainability Coordinator
Webcor Builders
LEEDuser Basic Member
40 thumbs up
Fri Aug 2, 2013, 6:45 pm

Average energy cost savings

NC-2009 EAp2:Minimum Energy Performance
posted by  Saju Varghese  on 

Does anybody know what is the average of energy cost savings reported to LEED/USGBC? We are just wondering to compare all projects overall. Thanks

3
CEO
ECON Group
LEEDuser Basic Member
126 thumbs up
Fri Aug 2, 2013, 3:58 pm

Type and Number of Boilers

NC-2009 EAp2:Minimum Energy Performance
posted by  Francesco Passerini  on 

In the building that I’m modelling there are two floors. On the ground floor the conditioned area is 3393m^2 and on the first floor it is 2689m^2.

3
Fri Aug 2, 2013, 3:52 pm

Exit Signs

EBOM-2009 MRc4:Sustainable Purchasing—Reduced Mercury in Lamps
posted by  Elena Grau  on 

Hi, I'd like to know which kind of luminaire means "exit signs". Does it means the constant light of the emergency lights? Thanks,

2
Sr. Electrical Engineer
Integrated Design Solutions
LEEDuser Expert
516 thumbs up
Fri Aug 2, 2013, 11:19 am

Warehouse - Windows as part of roll up dock doors

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  Charline SEYTIER  on 

We are working on a project that has a loading deck with an area inside at the perimeter of the warehouse that will be regularly occupied.

3
CEO, Co-owner.
ThemaVerde, France
LEEDuser Basic Member
15 thumbs up
Thu Aug 1, 2013, 2:48 pm