Sat Mar 7, 2015, 6:37 pm

PIlot Credit Reboot

Pilot-Credits PC74:No Environmental Tobacco Smoke
posted by  Gary Hansen  on 

We registered for PC 35 a while ago and now we are submitting the information to qualify for the PC, however the credit is not on the LEED website.

0

Scope of landlord change

CI-2009 WEc1:Water Use Reduction
posted by  Graham Langton  on 

Within our CI project (Office - 5 stories), there are landlord core areas including all toilets / washing facilities (same toilet block repeated on each floor).

1
Wed Dec 30, 2015, 10:48 pm

Water calculator

EBOM-2009 WEp1:Minimum Indoor Plumbing Fixture and Fitting Efficiency
posted by  Maria Rozatti  on 

There is somewhere a guide or guidance for completing the 2009 Water Use Reduction Calculator?????

1
Wed Sep 30, 2015, 11:07 pm

Service life of a piece of HVAC equipment?

NC-2009 EAc4:Enhanced Refrigerant Management
posted by  Rosemary Ziemann  on 

The link above for the 2007 ASHRAE Applications Handbook, HVAC Applications seems to be broken.

1
Tue Mar 10, 2015, 2:21 pm

Tree grates

CS-2009 SSc7.1:Heat Island Effect—Nonroof
posted by  sue bryant  on 

Can the metal grates used where trees are planted in a hardscape count as open paver area [as long as the 50% open grid is achieved]?

1
Mon Nov 30, 2015, 5:18 pm

ADA Parking Exclusion

CS-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Daniel Joseph  on 

Can we exclude ADA parking from the total parking capacity when considering the preferred parking 5% max?

1
Tue Mar 10, 2015, 6:27 pm

LEED CI Regional Priority Documentation

CI-2009 RPc1:Regional Priority
posted by  Bethany Beers  on 

It's not clear to me where to document the points for RPC's. At the end of each template, there is a check box for ID points, but nothing for RPC points.

1
Tue Mar 15, 2016, 7:53 pm

Cooling tower cycles

Pilot-Credits WEpc17:Cooling tower water use
posted by  Phuc Do  on 

Hi all, Our project is using Munters cooling tower in which the cooling tower cycles measured continuously and the dump cycle adjusted accordingly.

0

PAUs not serve the occupied areas

NC-2009 IEQp1:Minimum IAQ Performance
posted by  study topenergy  on 

A data center is applying for LEED-NC v2009. There are 5 PAUs (Primary Air Unit). 4 of them will serve the equipment rooms. One will serve the equipement rooms and office areas.

1