Farm on Roof

CI-2009 SSc1:Site Selection
posted by  Kristopher Croghan  on 

Our client currently has no landscape to maintain on site as this is a city office building. However, a roof farm is being considered.

0

SSc1 Path 12: EV Charging Stations

CI-2009 SSc1:Site Selection
posted by  Alaina Ladner  on 

How many EV charging stations are required to be provided to achieve this credit?

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Mon Sep 11, 2017, 9:42 pm

Currently Ongoing LEED Certification

CI-2009 SSc1:Site Selection
posted by  Nick Chiarelli  on 

Hi, The base building is currently pursuing LEED certification at the same time we are doing the tenant fit-out portion and pursuing LEED CI.

1
Mon May 13, 2013, 6:14 pm

SS CR 1 - Site Selection

CI-2009 SSc1:Site Selection
posted by  Harsharan Kaur  on 

Hi, We are planning to get our facility certified under LEED CI (USGBC) Ver. 3.0.

1
Mon Nov 3, 2014, 12:56 am

Parking availabilty

CI-2009 SSc1:Site Selection
posted by  Lavanya Veerappa  on 

The requriement of the credit - "parking availability" is to meet but not exceed local norms.

1
Wed Jul 25, 2012, 6:30 pm

LEED-CI 2009 SSc1 Option 2 Path 10

CI-2009 SSc1:Site Selection
posted by  Nicholas Vreeland  on 

We are attempting SSc1 Option 2 Path 10 for a CI project within a CS registered building. My question is that the form provided for this credit automatically populated 30 sec.

1
Mon Oct 14, 2013, 7:47 pm

Path 10

CI-2009 SSc1:Site Selection
posted by  Rodrigo Gomez Junco  on 

We are pursuing SSc1 Option 2 Path 10 for a CI project within a CS registered building. My question is, do I need the Tenant Lease Agreement from the CS project in order to document this credit?

1
Tue Jan 12, 2016, 3:42 pm
1
Mon Dec 7, 2009, 4:49 am

SSC1 Path 5: Heat Island Effect: Roof

CI-2009 SSc1:Site Selection
posted by  Elliot Young  on 

I am working on a project with an existing ballasted roof & am wondering if we could get this credit.

1
Fri Nov 30, 2012, 9:58 pm

Path 9

CI-2009 SSc1:Site Selection
posted by  Mike D  on 

Hello, If attempting Path 9, do the fixtures of the tenant space need to be included as well or do just the ones in the base build need to be included? Many thanks!

1
Tue May 6, 2014, 8:20 pm