How many EV charging stations are required to be provided to achieve this credit? The base building will be providing the infrastructure to add these as the demand increases, but they will install as many as are required at time of building opening to get this credit. How many should they upgrade?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for $15.95 »
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
August 26, 2017 - 6:48 pm
I would follow the LEED-NC ratios for the whole building, or for the space as long as they are allocated for that space.
Kristopher Croghan
Workplace Sector LeaderLS3P
3 thumbs up
September 11, 2017 - 5:42 pm
Did you successfully obtain a point for charging stations under the "Other Quantifiable Performance" for installing charging stations?