Sharing Whole-Building Energy and Water Usage Data

CI-2009 PIf1:Minimum Program Requirements
posted by  Kristen Streeter  on 

A client has asked for clarification of how this would happen so they can determine which box to check in the form.

2
Default Avatar
VP of Innovation
Sustainable Investment Group
LEEDuser Basic Member
110 thumbs up
Tue Jul 21, 2020, 9:36 pm

LEED CI project boundary

CI-2009 PIf1:Minimum Program Requirements
posted by  Drashti Dhirwani  on 

I am working on a 125,000 SF CI project, where approximately 2,500 SF space (2 private offices and a kitchen) was designed by a different designer, has a different contractor and is being cons

0

Incomplete Space within LEED-CI Multi-Use Building

CI-2009 PIf1:Minimum Program Requirements
posted by  Sara Zoumbaris  on 

Hello, We are working on a multi-use building that will house a hotel, residence, retail and a restaurant.

0

please post to more specific forums

CI-2009 PIf1:Minimum Program Requirements
posted by  Tristan Roberts  on 

Hi. This LEEDuser forum is specifically about completing the PI form 1. Most people's questions here are about either policy compliance with MPRs, or about the review process.

0

Non certified factory with new process area aiming certification

CI-2009 PIf1:Minimum Program Requirements
posted by  Valentin Grimaud  on 

Dear community, We have had a recent enquiry from a client. He has an existing industrial site, which is non certified. He wants to relocate another industrial activity in this site.

0

Very old CI 2009 registered project - can we still certify?

CI-2009 PIf1:Minimum Program Requirements
posted by  Eric Thompson  on 

Hi I'm helping a colleague who has a project that was registered in 2011 for LEED CI 2009 and construction completed / substantial completion in 2011.

1
Thu Nov 12, 2015, 8:00 pm

MPR 6 for Single Tenant Building

CI-2009 PIf1:Minimum Program Requirements
posted by  Jonathan Weiss  on 

We are working on a project where we are the sole tenant in the building. Can we use the whole building meters for our MPR6 reporting if there is no other user in the building?

1
Fri Nov 21, 2014, 5:24 pm

Contacting the USGBC and Combining Tenant Spaces

CI-2009 PIf1:Minimum Program Requirements
posted by  CHRISTIAN LUTJEN  on 

Hello, we have been trying to get an answer from the USGBC for two days short of a full month now.

1
Thu Nov 12, 2015, 4:40 pm

MPR #6

CI-2009 PIf1:Minimum Program Requirements
posted by  Tracy Baker  on 

I am working on a CI project that is within a LEED Platinum building. The base building did not install tenant submetering. It does, however share whole building energy use data with the USGBC.

1
Wed Oct 22, 2014, 7:45 pm

Leed boundary for commercial interior

CI-2009 PIf1:Minimum Program Requirements
posted by  Elena Gonzi  on 

Hi, I have some question about LEED Commercial Interior certification : 1) Situation: we have a offices building that has a basement in common with other two offices buildings.

1
Wed Dec 30, 2015, 5:09 pm