EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Gustavo De las Heras Izquierdo on
Hallo, According to the BMS and HVAC subcontractor, the sensors do not need to be calibrated, particularly CO sensors and chilled water temperature sensors.
Interpretation doubt
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Carolina Vergnano on
Hello, I've got a doubt about the time that we should develop the breakdown of energy.
How to define categories
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Noriko Nagazumi on
Hello there, There is a sample summary of energy and metering capacity on page 200 of the reference guide, and some explanation on "Energy Use Breakdown" on page 198 saying that significant appli
LEED V3 Vs V4
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by VISHESH AGARWAL on
Advanced energy metering: if a project have all end use submeter but no have enery reporting software or BAS.
What to do?
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Paola Figueiredo on
Our project team is working on LEED EBOM certification of an industrial compound, and there is a question we are not so sure about and we believe one of you may be able to help.
Tenant submetering
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Gustavo De las Heras Izquierdo on
I’ve read in the Bird’s Eye View Section that “Tenant submetering would not alone qualify for this credit. […]”.
Tenant Electricity Meters
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Mitch Gascoyne on
Does anyone have any experience with tenant sub-metering and compliance with this credit?
Airflow metering
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Tapio Peltonen on
Our project building has central air-handlers, which provide heating and cooling for the tenant spaces i.e. heating and cooling by air only.
Minimum Performance Measuring Time
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Marina Andrade on
Greetings, We have a doubt about the credit EA C3.2 from LEED EB O&M. What is the minimum time to measure performance of the major’s building systems by the breakdown of energy?
Performance period duration
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Charalampos Giannikopoulos on
The LEED Online form requests that “monthly and annual summaries of the metered energy usage for each of the subsystems”.