Interpretation doubt

EBOM-2009 EAc3.2:Performance Measurement—System-Level Metering
posted by  Carolina Vergnano  on 

Hello, I've got a doubt about the time that we should develop the breakdown of energy.

1
Tue Nov 29, 2011, 11:40 am

Calibration

EBOM-2009 EAc3.2:Performance Measurement—System-Level Metering
posted by  Gustavo De las Heras Izquierdo  on 

Hallo, According to the BMS and HVAC subcontractor, the sensors do not need to be calibrated, particularly CO sensors and chilled water temperature sensors.

1
Tue Aug 29, 2017, 3:45 pm

How to define categories

EBOM-2009 EAc3.2:Performance Measurement—System-Level Metering
posted by  Noriko Nagazumi  on 

Hello there, There is a sample summary of energy and metering capacity on page 200 of the reference guide, and some explanation on "Energy Use Breakdown" on page 198 saying that significant appli

1
Mon Jan 25, 2016, 9:46 pm

What to do?

EBOM-2009 EAc3.2:Performance Measurement—System-Level Metering
posted by  Paola Figueiredo  on 

Our project team is working on LEED EBOM certification of an industrial compound, and there is a question we are not so sure about and we believe one of you may be able to help.

1
Thu Feb 16, 2012, 10:28 pm

LEED V3 Vs V4

EBOM-2009 EAc3.2:Performance Measurement—System-Level Metering
posted by  VISHESH AGARWAL  on 

Advanced energy metering: if a project have all end use submeter but no have enery reporting software or BAS.

1
Fri Jun 3, 2016, 8:50 pm

Tenant Electricity Meters

EBOM-2009 EAc3.2:Performance Measurement—System-Level Metering
posted by  Mitch Gascoyne  on 

Does anyone have any experience with tenant sub-metering and compliance with this credit?

1
Thu Feb 16, 2012, 10:33 pm

Tenant submetering

EBOM-2009 EAc3.2:Performance Measurement—System-Level Metering
posted by  Gustavo De las Heras Izquierdo  on 

I’ve read in the Bird’s Eye View Section that “Tenant submetering would not alone qualify for this credit. […]”.

1
Mon May 2, 2016, 5:59 pm

Airflow metering

EBOM-2009 EAc3.2:Performance Measurement—System-Level Metering
posted by  Tapio Peltonen  on 

Our project building has central air-handlers, which provide heating and cooling for the tenant spaces i.e. heating and cooling by air only.

1
Tue Oct 16, 2012, 1:02 pm

Minimum Performance Measuring Time

EBOM-2009 EAc3.2:Performance Measurement—System-Level Metering
posted by  Marina Andrade  on 

Greetings, We have a doubt about the credit EA C3.2 from LEED EB O&M. What is the minimum time to measure performance of the major’s building systems by the breakdown of energy?

1
Mon Feb 17, 2014, 7:39 pm

Instantaneous and/or totalized

EBOM-2009 EAc3.2:Performance Measurement—System-Level Metering
posted by  James Gray  on 

For natural gas metering applications, is continuous logging of instantaneous flows a requirement? Most meters just put out totalized pulses, so I'm assuming that's fine... Any thoughts?

0