EAc2.3 - Ongoing Cx forms
EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioningposted by Alexis Voeltner on
Hi Hannah, do you have an example of what the on-going commissioning test form should look like?
Scope of comissioning
EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioningposted by Iris Amdur on
Hello- We're working on a building that is not owner occupied and the tenant has 48 additional pieces of equipment that are not a part of the base building that are currently only being monitored
Ongoing Cx Requirements
EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioningposted by Colleen Collins on
I have a question regarding EA2.3 As I understand it, it appears that the ongoing Cx process effectively begins with EAc2.1 and EAc2.2.
BMS
EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioningposted by Gustavo De las Heras Izquierdo on
Hallo, We are working on two projects located in Mexico DF. One of them doesn't have a BMS and the other has a BMS but it does not provide trend graphs.
Comments from a LEED review
EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioningposted by Raphael Sperry on
We just received comments on a review of this credit I am trying to understand. For this project, we actually had an approved MV plan from LEED NC credit EAc5.
Doing both the Level II assessment and credit EA2.3 "ongoing Cx"
EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioningposted by Tom Kennedy on
Our team sees benefit to doing both, and making a deliberate effort to place energy-items into either the "audit" or "Cx" category (so we don't duplicate too much).
CxA selection
EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioningposted by Melissa Merryweather on
In LEED NC there are explicit instructions as to whom is eligible to be the projects' CxA. I don't see reference to this in LEED EBOM.
On-going Commissioning
EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioningposted by Tracy Smith on
We have already been awarded EAc2.1 and EAc2.2. To get these points we did a retro commissioning report. When we resubmit, we are considering going for EAc2.3.
EAc2.1 work
EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioningposted by Elizabeth Crenshaw Hammitt on
From reading these comments, it seems like any work done EAc2.1 MAY NOT count toward this credit.