Comments from a LEED review

EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioning
posted by  Raphael Sperry   on 

We just received comments on a review of this credit I am trying to understand. For this project, we actually had an approved MV plan from LEED NC credit EAc5.

1
Tue Feb 21, 2012, 10:36 pm

EAc2.3 - Ongoing Cx forms

EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioning
posted by  Alexis Voeltner  on 

Hi Hannah, do you have an example of what the on-going commissioning test form should look like?

1
Tue Jan 20, 2015, 6:52 pm

Scope of comissioning

EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioning
posted by  Iris Amdur  on 

Hello- We're working on a building that is not owner occupied and the tenant has 48 additional pieces of equipment that are not a part of the base building that are currently only being monitored

1
Fri Mar 2, 2012, 8:51 pm

Ongoing Cx Requirements

EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioning
posted by  Colleen Collins  on 

I have a question regarding EA2.3 As I understand it, it appears that the ongoing Cx process effectively begins with EAc2.1 and EAc2.2.

1
Thu Nov 7, 2013, 9:16 pm
1
Fri Jan 21, 2011, 5:53 pm

BMS

EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioning
posted by  Gustavo De las Heras Izquierdo  on 

Hallo, We are working on two projects located in Mexico DF. One of them doesn't have a BMS and the other has a BMS but it does not provide trend graphs.

1
Thu Jan 12, 2017, 11:05 pm

Doing both the Level II assessment and credit EA2.3 "ongoing Cx"

EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioning
posted by  Tom Kennedy  on 

Our team sees benefit to doing both, and making a deliberate effort to place energy-items into either the "audit" or "Cx" category (so we don't duplicate too much).

2
Mon May 15, 2017, 4:27 am

CxA selection

EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioning
posted by  Melissa Merryweather  on 

In LEED NC there are explicit instructions as to whom is eligible to be the projects' CxA. I don't see reference to this in LEED EBOM.

3
Mon Apr 25, 2016, 4:08 pm

On-going Commissioning

EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioning
posted by  Tracy Smith  on 

We have already been awarded EAc2.1 and EAc2.2. To get these points we did a retro commissioning report. When we resubmit, we are considering going for EAc2.3.

3
Tue Jun 23, 2015, 4:09 pm

EAc2.1 work

EBOM-2009 EAc2.3:Existing Building Commissioning—Ongoing Commissioning
posted by  Elizabeth Crenshaw Hammitt   on 

From reading these comments, it seems like any work done EAc2.1 MAY NOT count toward this credit.

5
Fri Feb 8, 2013, 10:35 pm