EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by Patrick Cellie on
I am working with a convention center currently certified Silver in the v2009 EBOM rating system. The owners are monitoring data with the goal to re-certify when the time comes.
Minimum number of equipments to be audited
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by ESD Singapore on
Hi all, The project that we are working on would like to go pursue this credit using ASHRAE level 2 commissioning audit path. However, this project has a large quantity of AHUs and FCUs (approx.
Retrocommissioning - Systems Requirements
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by Nate Eppley on
I am working on a cultural center performance space in San Diego with very few HVAC system components.
Existing Building Commissioning
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by sebastian castañeda on
Hello. I am a student who is interested in learning about the methodology of LEED certification and there are some points that I do not clear.
CX EBOM EAc2.1
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by Katherine Phelps on
Looking for a Building commissioning service provider in Southern Massachusetts.
Update of the ASHRAE Level II Audit report
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by David ESPAGNET on
Hello everybody. The Ashrae Audit realized for the LEED EBOM project i am in charge was completed more than 2 years before the performance period.
first commissioning cycle
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by ethan adams on
OK, so.....if I haven't done any updates to the building in the 24 months prior to application for EBOM, then it's impossible to get EAc2.3, no matter how much the company might invest immediately
Upgrades