Further normalized EUI
EBOM-2009 EAp2:Minimum energy efficiency performanceposted by SENGATHIR SELVAN on
Hi there, in our efforts to achieve LEED EBOM certification for a production facility (garment washing plant) in Dhaka, we have implemented energy conservation measures.
CASE 2 and EAP2 Cumpliance
EBOM-2009 EAp2:Minimum energy efficiency performanceposted by João Gaio on
Hi, We are working on a multi tenant enclosed mall with aproximmatly 120.000, to be certified LEED 2009 EBOM. In Portfolio Manager, "enclosed mall" is not eligible to receive EnergyStar score.
Solar street light
EBOM-2009 EAp2:Minimum energy efficiency performanceposted by satheesh M on
Hi, In our project 36 No of 25 Watts individual solar street light is available.
Absorption Chiller - District Heating
EBOM-2009 EAp2:Minimum energy efficiency performanceposted by Ralf Lehmann on
In my project there is an absorption chiller supplied by district heating. The building itself is also heated by district heating.
Data Center in Portfolio Manager
EBOM-2009 EAp2:Minimum energy efficiency performanceposted by Charalampos Giannikopoulos on
How should a Data Center building facility be included in the Portfolio Manager? The building hosts the data center and the supporting offices.
EAp2 X Multiple Building
EBOM-2009 EAp2:Minimum energy efficiency performanceposted by Adriana Hansen on
Dears, We would like to solve out some questions about the LEED EB certification process. In this case we have a boundary area with 4 towers.
Discovery of Streetlights, changes Energy Performance
EBOM-2009 EAp2:Minimum energy efficiency performanceposted by Janna Nash on
I am not sure how to approach a recent discovery.