Option 1 Path 2 Temperature and Humidty Requirements

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Amy Harmon  on 

Path 1 indicates flush-out needs to be accomplished with 14,000 cu ft. of OA per sq. ft. of floor area while maintaining an internal temperature of at least 60 deg F and no more than 60% RH.

3
Default Avatar
Scheeser Buckley Mayfield
LEEDuser Basic Member
0 thumbs up
Fri Apr 22, 2016, 2:07 pm

Multi-Family Residential Options

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Alexis Thompson  on 

I've seen a lot of comments and guidance regarding Option 2 for air quality testing in residential applications, however no guidance on Option 1.

2
Artist, Curator, Writer
Teresa Stern Arts
LEEDuser Basic Member
20 thumbs up
Thu Jan 28, 2016, 6:29 pm

What "floor area" to use

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Lyle Axelarris  on 

Since the credit template is not linked to the Gross Floor area in PIf2 (as it is in other relevant credits), does that mean the floor area in the flushout calcs should be net area, as it is done f

4
Building Enclosure Consultant
BPL Enclosure
LEEDuser Basic Member
58 thumbs up
Thu Oct 8, 2015, 9:15 pm

cost of IAQ testing?

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Tristan Roberts  on 

What costs have you found for IAQ testing under this credit? Per SF? Per test? Every project is different but I'm curious for your anecdotal experience, for updating our Cost of LEED report.

2
Default Avatar
LEED AP (O+M)
4 Elements Group
LEEDuser Basic Member
34 thumbs up
Mon Jul 13, 2015, 7:01 pm

Occupancy Date Comments

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Michelle Rosenberger  on 

I have received 2 review comments in the past few weeks that take issue with the fact that the "Substantial Completion" or "Estimated date that project will be ready for occupancy" date on the Pfor

3
Mechanical Engineer
Integral Group
LEEDuser Expert
342 thumbs up
Fri Jun 12, 2015, 10:48 pm

direct reading instruments

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Kelly Bruvik  on 

Can direct reading instruments be used to measure VOCs and PM10? Another user asked specifically about the GrayWolf IAQ equipment and I was also wondering if it can be used for EQc3.2.

2
Fri Feb 27, 2015, 4:23 pm

Air Quality Testing after completion

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Mike Stopka  on 

Hello I have a project that is very close to LEED Gold. I am trying to lock down one more point. The project is in the final phase of the construction submission for LEED.

6
Tue Dec 9, 2014, 9:03 pm

Mold Testing Standards

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Susan Walter  on 

We have a project and the owner wants to include testing for mold. We had flooding in a project and two AHUs now show signs of mold.

3
Thu Nov 13, 2014, 9:09 pm

Comment on Value and Purpose of IEQc3.2

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Dale Walsh  on 

As a Certified Industrial Hygienist with 28 years of experience conducting IAQ assessments and a Masters Degree in Toxicology/Industrial Hygiene with a thesis on new carpet emissions I want to stat

2
Default Avatar
LEEDuser Basic Member
1 thumbs up
Wed Sep 24, 2014, 1:45 am

Performing testing under Option 2 - number of samples

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Adriana Hansen  on 

For performing testing under Option 2 (IAQ Testing), for a singular space above 25,000 sf served by several similar AHU systems, could it be acceptable using the “1/25,000 SF or each contiguous are

3
Manager
CTE - Centro de Tecnologia de Edificações
LEEDuser Basic Member
80 thumbs up
Tue May 20, 2014, 4:44 pm