Path 1 indicates flush-out needs to be accomplished with 14,000 cu ft. of OA per sq. ft. of floor area while maintaining an internal temperature of at least 60 deg F and no more than 60% RH. However, as I'm reading through Path 2, there is no mention of maintaining a certain internal temperature or relative humidity. When I go to submit the temperature and humidity readings using Path 2 along with all the supporting documentation, will I be denied credit for this point if I have any out of range temperature and/or humidity points even though Path 2 does not temperature and humidity limitations? Thanks!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for $... »
Dave Hubka
Practice Leader - SustainabilityEUA
LEEDuser Expert
544 thumbs up
April 20, 2016 - 12:31 pm
The corrective action flush out is not specified to meet a pre-determined duration or temp/RH limit.
I am not aware of any LEED Interpretation or CIR that sets precedence on this issue.
Amy Harmon
Scheeser Buckley MayfieldApril 22, 2016 - 9:38 am
David,
By corrective action flush-out, do you mean the "post-occupancy" flush-out?
Thanks!
Dave Hubka
Practice Leader - SustainabilityEUA
LEEDuser Expert
544 thumbs up
April 22, 2016 - 10:07 am
Corrective action flush-out must occur pre-occupancy. Resample and confirmation must also occur before occupancy.