Restroom ventilation
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Alexia Anastassiadis on
We are working on a major renovation project and the restrooms have natural ventilation. Do we have to provide additional mechanical exhaust to comply with ASHRAE?
Natural Roof Top Ventilator
NC-2009 IEQp1:Minimum indoor air quality performanceposted by SAMY Chamy on
Dear Concern:- The proposed project consist of 200000 sq.ft area in a single space It is totally metal building the roof top have natural ventilators and the exterior wall have louvers in all sid
2 different system in LEED Boundary
NC-2009 IEQp1:Minimum indoor air quality performanceposted by SW LEE on
Hi, In our project, we have 2 different ventilation system.
IEQP1_Sample Letter of Appeal
NC-2009 IEQp1:Minimum indoor air quality performanceposted by susan eguia on
Hi, Is anyone whom could share sample template for appeal to USGBC. Also, what is the fastest way to contact the assigned reviewer for the project aside from feedback. Appreciate any assistance.
Zone Calculation Ds% for VAV System
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Marina Andrade on
I received this question in IEQp1: "The ventilation calculations indicate that the value of the flow rate of air projected under the condition tested (DS) was modeled as 100% level for each of th
Administrative Wing of Industrial Facility
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Lorena Moscoso on
Dear all: There is an administrative wing of an industrial facility and my questions are: 1.
PAUs not serve the occupied areas
NC-2009 IEQp1:Minimum indoor air quality performanceposted by study topenergy on
A data center is applying for LEED-NC v2009. There are 5 PAUs (Primary Air Unit). 4 of them will serve the equipment rooms. One will serve the equipement rooms and office areas.
Natural Ventilation - Brewery Local Distribution Building
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Summer Gorder on
I am working on a Brewery Campus expansion that includes a small local distribution building that is utilizing natural ventilation.
Calculating Ds for LEED 62MZCalc
NC-2009 IEQp1:Minimum indoor air quality performanceposted by William Beechinor on
Hello, I am currently trying to calculated Ds for the cooling condition for a project I an working on.
air-side economizer, how to input in calculator
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Courtney Royal on
Our project is a one floor (on the 30th) LEED-CI project gut renovation project.